Petition for determination of transmission tariff for Evacuation of Power from Solar Energy Zones in the Northern Region

Summary:

### **Case Summary**

* **Petitioner**: Power Grid Corporation of India Limited (PGCIL)
* **Respondents**: Uttar Pradesh Power Corporation Limited and 14 others
* **Petition Subject**: Determination of transmission tariff for the period 2024–29 for the project titled
**“Transmission System Strengthening Scheme for Evacuation of Power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-II-Part-A1”**.

### **Key Developments During Hearing**

* PGCIL submitted that it had filed all necessary documents and requested the Commission to approve the tariff.

### **Commission’s Directives**

#### **To the Petitioner (PGCIL):**

* **Implead CTUIL** as a respondent and file a **revised memo of parties within 2 days**.
* **Provide an affidavit** within 2 weeks covering:

1. Explanation for setting the **Scheduled COD (SCOD)** as **3.3.2022**, despite earlier scheduling for December 2021.
2. **Justification for delay** of 1 year between allocation by CTUIL (Jan 2020) and Investment Approval (Jan 2021).
3. Explanation for **variation in site preparation costs** – ₹223.79 lakh incurred vs. ₹20 lakh estimated.
4. Confirmation and justification for **₹13.64 lakh spent on Building & Colony works**.
5. Justification for **54.48% cost escalation** in transformer procurement.
6. Submit **awarded cost vs. completion cost comparison**.
7. Resubmit **Form-12 with exact date of completion**, not just month.
8. Justify **delay in material supply** (2 years and 5 months delay from NOA issuance).
9. Provide **activity-wise time delay analysis** in specified tabular format.

#### **To CTUIL (Central Transmission Utility of India):**

* **File affidavit within 2 weeks**, addressing:

1. Provide **completion schedule** for the associated Phase-II-Part-A scheme.
2. Confirm whether **ICT commissioning was deferred** and under which regulatory provision.
3. Clarify whether the transmission asset is part of a **common or beneficiary-specific transmission system**, with supporting details.

#### **To All Respondents (including CTUIL):**

* **File replies within 2 weeks**, with a copy to PGCIL.
* PGCIL may file its **rejoinder** within the following 2 weeks.

### **Next Hearing**

* The petition is scheduled for the **next hearing on 16 September 2025**.