Petition for Truing up and the determination of transmission tariff for transmission asset at Saharanpur (PG) in the Northern Region – EQ
Summary:
—
## 📌 Case Overview
* **Petitioner:** Power Grid Corporation of India Ltd. (PGCIL)
* **Respondents:** Uttar Pradesh Power Corporation Ltd. (UPPCL) & 15 others
* **Subject:**
* **Truing up** of transmission tariff for 2019–24.
* **Determination** of transmission tariff for 2024–29.
* Assets: **2 Nos. 220 kV line bays at Saharanpur (PG)** in Northern Region.
* **Date of Hearing:** 26th August 2025.
* **Coram:** Chairperson Jishnu Barua; Members Ramesh Babu V., Harish Dudani, Ravinder Singh Dhillon.
—
## ⚡ Proceedings
* PGCIL’s representatives appeared, along with advocates for UPPTCL.
* **UPPTCL filed a reply** opposing/raising issues.
* **PGCIL requested 1 week** to file its **rejoinder**.
* UPPTCL requested that the matter be reserved for order.
—
## 🏛️ Commission’s Directions
1. PGCIL to file its **rejoinder within one week**.
2. Subject to rejoinder filing, the **order has been reserved**.
—
## âś… Current Status
* Petition is **reserved for order** after completion of pleadings.
* Final decision on tariff truing up (2019–24) and tariff determination (2024–29) for the Saharanpur line bays will be issued by CERC once rejoinder is considered.
—
For more information please see below link:
Related posts:
- Petition for Truing Up of and determination of transmission tariff for the S/C Kankroli-Jodhpur Transmission Line in the Northern Region – EQ
- Petition for Truing Up and determination of transmission tariff of “Additional Special Energy Meters” in Northern Region – EQ
- Petition for Truing Up and determination of transmission tariff for the “System Strengthening Scheme in the South-Western Part of the Northern Grid (Part- B)” in the Northern Region – EQ
- Petition for Truing up and determination of transmission tariff at Saharanpur (PG) in the Northern Region – EQ