Petition of GERC (Licensee’s Power to Recover Expenditure incurred in providing Supply and other Miscellaneous Charges) and (Electricity Supply Code and Related Matters) Regulations – EQ

Summary: — ## **Case Details** * **Petitioner**: HPCL LNG Limited (represented by Adv. Sudha Reddy). * **Respondents**: 1. Paschim Gujarat Vij Company Ltd. (PGVCL). 2. Gujarat Energy Transmission Corporation Ltd. (GETCO). * **Bench (Coram)**: Mehul M. Gandhi (Member) & S.R. Pandey (Member). * **Legal Basis**: Petition filed under **Sections 86 (1) (c), (i), (k), 40 […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the Electricity Act of the PPA between Torrent Power Ltd. and Adani Renewable Energy Eight Ltd. under the Change in Law – EQ

Summary: — # ⚖️ Case Details * **Forum:** GERC, Gandhinagar. * **Petition No.:** 2053 of 2022. * **Filed under:** Section 86(1)(b) of the Electricity Act, 2003 + Article 9 of PPAs (12.05.2021). * **Petitioner:** Torrent Power Ltd. – Distribution (counsel: Abhishek Munot, Kunal Kaul, Jignesh Langalia, Luna Pal). * **Respondent No.1:** Adani Renewable Energy Eight […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the Electricity Act of the PPA of certain Force Majeure events to the extent prayed – EQ

Summary: — # ⚖️ Case Details * **Forum:** GERC, Gandhinagar. * **Petition No.:** 2531 of 2025 + IA No. 75 of 2025. * **Petitioner:** *Juniper Green Beam Pvt. Ltd.* (counsel: Ms. Parichita Chowdhury et al.). * **Respondent:** *Gujarat Urja Vikas Nigam Ltd. (GUVNL)* (counsel: Ms. Srishti Khindaria et al.). * **Coram:** Mehul M. Gandhi & […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the GERC (Conduct of Business) Regulations of the evacuation infrastructure at the behest – EQ

Summary: — # ⚖️ Case Details * **Forum:** GERC, Gandhinagar. * **Petition No.:** 2519 of 2025. * **Filed under:** Sections 86(1)(c), (e), (f) of the Electricity Act, 2003 + Regs. 80 & 82 of GERC Conduct of Business Regulations, 2004. * **Petitioner:** *Cleanmax Vayu Pvt. Ltd.* * Counsel: Ld. Adv. Mr. Mridul Gupta. * **Respondent:** […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the Guidelines for Tariff from Grid connected Renewable Energy Power Projects with Energy Storage Systems – EQ

Summary: — # ⚖️ Case Details * **Forum:** Gujarat Electricity Regulatory Commission (GERC). * **Petition No.:** 2533 of 2025. * **Petitioner:** Torrent Power Limited (represented by Mr. Jignesh Langalia & Ms. Luna Pal). * **Coram:** Mehul M. Gandhi & S. R. Pandey (Members). * **Date of Order:** 29.08.2025. — # 📑 Subject Matter * Petition […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition for procurement and adoption of tariff from Grid connected 250 MW Wind (Phase IX) – EQ

Summary: — # ⚖️ Case Details * **Forum:** GERC, Gandhinagar. * **Petition No.:** 2528 of 2025. * **Filed under:** Section 63 + Section 86(1)(b), Electricity Act, 2003. * **Petitioner:** Gujarat Urja Vikas Nigam Ltd. (GUVNL). * Representative: Mr. Rushabh Soni. * **Respondents:** 1. KPI Green Energy Ltd. – Mr. Karmit Sheth. 2. Juniper Green Energy […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the GERC (Conduct of Business) Regulation of the evacuation infrastructure till the commissioning of the entire capacity of 40 MW of Wind Power Project – EQ

Summary: — # ⚖️ Case Details * **Forum:** GERC, Gandhinagar. * **Petition No.:** 2504 of 2025 + IA No. 52 of 2025. * **Petitioner:** *Sarjan Realties Pvt. Ltd.*, Pune. * Counsel: Ld. Adv. Aditya Singh. * **Respondent:** *Gujarat Energy Transmission Corp. Ltd. (GETCO)*. * Counsel: Ld. Adv. Aneesh Bajaj with Mr. Shobhraj Jayswal. * **Coram:** […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the GERC (Conduct of Business) Regulations for construction of the evacuation infrastructure of 25 MW of Wind- Solar Hybrid Power to intra-State Transmission system – EQ

Summary: — # ⚖️ Case Details * **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar. * **Petition No.:** 2472 of 2025. * **Filed under:** Sections 86(1)(c), (e), (f) of the Electricity Act, 2003 + Regs. 80 & 82 of GERC Conduct of Business Regulations, 2004. * **Subject:** * Extension of time up to **31.12.2025** for construction […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of GERC (Conduct of Business) Regulations of PPA and Change in Law Event – EQ

Summary: — # ⚖️ Case Details * **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar. * **Petition No.:** 2200 of 2023. * **Filed under:** Section 86(1)(f) of the Electricity Act, 2003 + Regulation 23 of GERC (Conduct of Business) Regulations, 2004 + Article 9 of the PPA dated 23.04.2021. * **Subject:** Seeking **“In-Principle” declaration** that Notifications […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ

Petition of the GERC (Conduct of Business) Regulations of the Evacuation Line along with bays and metering system of the 4.15 MW Solar – Wind Hybrid Project – EQ

Summary: — # ⚖️ Case Details * **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar. * **Petition No.:** 2438 of 2025. * **Filed under:** Section 86 of the Electricity Act, 2003 + GERC Conduct of Business Regulations, 2004. * **Policy basis:** Gujarat Renewable Energy Policy, 2023 + Tariff Order dated 31.08.2024. * **Subject:** Request for extension […]

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Davanagere Power Transmission Ltd – EQ