In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission Licence and other related matters) Regulations to Chitradurga Bellary REZ Transmission Ltd – EQ

Summary: — ## 📌 Case Overview * **Petitioner:** *Bikaner–Neemrana Transmission Limited* (now **POWERGRID Bikaner Neemrana Transmission Limited**, 100% subsidiary of PGCIL) * **Subject:** Application for **inter-State transmission licence** under Sections 14 & 15 of the Electricity Act, 2003 read with CERC (Procedure, Terms & Conditions for grant of Transmission Licence) Regulations, 2024. * **Order Date:** […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

BUSINESS PLAN Approval of Business Plan for MYT Control Period from FY 2025-26 to FY 2029-30 – EQ

Summary: — ## 📌 Case Overview * **Commission:** Joint Electricity Regulatory Commission (JERC) * **Petitioner:** Electricity Department, Andaman & Nicobar Islands (A\&N) * **Respondent:** None (suo motu compliance petition) * **Subject:** Approval of **Renewable Power Procurement Plan & RPO compliance** for **FY 2022-23 & FY 2023-24**. * **Order Date:** January 2025 — ## ⚡ Background […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

In the matter with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to Transmission License to Fatehgarh II and Barmer I PS Transmission Limited – EQ

Summary: — ## 📌 Case Overview * **Petitioner:** Fatehgarh II and Barmer I PS Transmission Limited *(now POWERGRID Fatehgarh Barmer Augmentation Transmission Limited, 100% subsidiary of PGCIL)* * **Subject:** Application under Sections 14 & 15 of the Electricity Act, 2003 read with **Transmission Licence Regulations, 2024** for grant of **inter-State transmission licence**. * **Order Date:** […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

In the matter of the CERC (Procedure, Terms and Conditions for Grant of Trading Licence and other related matters) Regulations for inter-State trading of electricity in all States and Union Territories of India – EQ

Summary: — ## 📌 Case Overview * **Petitioner:** *Aayuda Energy Ventures LLP (AEVLLP)*, Delhi. * **Subject:** Application under Section 15(1) of the Electricity Act, 2003 & CERC Trading Licence Regulations, 2020 for **Category V trading licence**. * **Order Date:** 14th August 2025 * **Coram:** Chairperson Jishnu Barua & Members Ramesh Babu V., Harish Dudani, Ravinder […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

BUSINESS PLAN ORDER Approval of Business Plan for 4th Multi-Year Tariff Control Period from FY 2025-26 to FY 2029-30 for ED, Puducherry – EQ

Summary: — ## **Joint Electricity Regulatory Commission (JERC) – Petition No. 49/2024** ### 📌 Case Details * **Petitioner:** Electricity Department, UT of Lakshadweep * **Subject:** Approval of **Renewable Power Procurement Plan (RPO compliance)** for **FY 2022-23 & FY 2023-24**. * **Relief Sought:** 1. Approval of RPO compliance for FY 22-23 & FY 23-24. 2. Permission […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Petition for Adoption of tariff discovered under Competitive Bidding Process from 250 MW Grid connected Solar PV Power Projects anywhere in India – EQ

Summary: — ## **Gujarat Electricity Regulatory Commission (GERC) – Daily Order** ### 📌 Case Details * **Petition No.:** 2484 of 2025 * **Petitioner:** Gujarat Urja Vikas Nigam Limited (GUVNL) * **Respondents:** 1. Welspun Renewable Energy Ltd. – 50 MW @ ₹2.60/unit 2. Avaada Energy Pvt. Ltd. – 100 MW @ ₹2.60/unit 3. SAEL Industries Ltd. […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Petition of GERC (Conduct of Business) Regulations for commissioning of 4 MW AC Solar Power Project at District- Bharuch – EQ

Summary: — ## **Gujarat Electricity Regulatory Commission (GERC) – Daily Order** ### 📌 Case Details * **Petition No.:** 2479 of 2025 * **Petitioner:** *M/s. Shree Ganesh Enterprise* (Proprietor: Mr. Jaydip M. Patel) * **Respondents:** 1. Gujarat Energy Transmission Corporation Ltd. (GETCO) 2. Gujarat Urja Vikas Nigam Ltd. (GUVNL) 3. Dakshin Gujarat Vij Company Ltd. (DGVCL) […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Petition for Procurement of Power by Distribution Licensees and Others from Wind-Solar Hybrid Projects from its 40 MW Hybrid Power Plant – EQ

Summary: — ## **Gujarat Electricity Regulatory Commission (GERC) – Daily Order** ### 📌 Case Details * **Petition No.:** 2481 of 2025 * **Petitioner:** *Onix Two Enersol Pvt. Ltd.* * **Respondent:** Gujarat Energy Transmission Corp. Ltd. (GETCO) * **Subject:** Petition under Section 86 of the Electricity Act, 2003 read with GERC’s *Tariff Framework Order No. 01/2024* […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Tariff Order Approval of Business Plan for Multi Year Control for DNH & DD Power Corporation Ltd – EQ

Summary: — ## **Joint Electricity Regulatory Commission (JERC) – Final Order** ### 📌 Case Details * **Petition No.:** 27/2024 * **Petitioner:** Electricity Department, UT of Dadra & Nagar Haveli and Daman & Diu (DNH\&DD) * **Respondent:** None (suo-motu compliance petition) * **Subject:** Approval of **Renewable Power Procurement Plan (RPO compliance)** and **approval of shortfall compensation**. […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Petition of the Electricity Act for purchase of power through Competitive Bidding Process from 250 MW Grid connected Solar Photovoltaic Power Projects – EQ

Summary: — ## **Case Summary – Gujarat Urja Vikas Nigam Ltd. (GUVNL) vs. Welspun Renewable Energy Ltd. & Ors.** **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar **Petition No.:** 2484 of 2025 **Order Date:** 29 July 2025 **Coram:** * Mehul M. Gandhi, Member * S.R. Pandey, Member — ### **1. Case Background** * **Petitioner:** Gujarat Urja […]

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ