IHQ of MoD (Army)-(OSCC) issue Tender for Supply and constr of Off Grid Solar Power Plant of Sys – EQ

IHQ of MoD (Army)-(OSCC) issue Tender for Supply and constr of Off Grid Solar Power Plant of Sys – EQ

0
0

Summary:

## ๐Ÿ“Œ Project Scope

* Supply & construction of **3ร— Off-grid 50 kW solar power plants** near Leh (within 350 km).
* Issued by **HQ 14 Corps / 21 Engineer Regiment**.
* Includes full system (PV, inverter, BESS, housing, cabling, protections, foundations, handover).

## ๐Ÿ“… Timeline

* **50% stores (incl. foundations):** within 60 days of SO.
* **100% stores:** within 120 days.
* **Construction + handover:** within 360 days of SO.
* **IIT/NIT vetting:** mandatory within 30 days of SO.

## ๐Ÿ”ง Key Technical Specs

* **Solar PV:** ALMM-listed, mono half-cut, >20% efficiency, 400 W+; dual tilt; withstand 200 km/h wind, high snow load, โ€“40 ยฐC to +40 ยฐC.
* **Battery Bank:** Gel VRLA, 384 V 1000 Ah, 80% DOD, 5000 cycles (replacement included), heated enclosure.
* **Inverter:** 60 kW hybrid, supports PV/wind/DG/battery; MPPT; seamless switching; remote monitoring.
* **Protection:** SPD Type I/II, LA, IS 3043 earthing, AC/DC distribution with metering.
* **Housing:** PUF prefab shelter with heating, south-facing glazing.
* **Warranty/AMC:** 5 years comprehensive.

## ๐Ÿ’ฐ Commercial Terms

* **EMD:** 2% of tender cost.
* **Performance BG:** 10% of SO value, released over 5 years.
* **AMC BG:** 5% before final BG release.
* **Payment milestones per shelter:** 25% (50% stores), 25% (100% stores), 10% (foundation), 15% (erection), 10% (finishes), 15% (handover).
* **LD:** 0.5%/week, max 10%.
* **Repeat order:** Up to 50% within 6 months.

## ๐Ÿ“‘ Eligibility & Compliance

* **Financials:** Solvency โ‰ฅ50% contract value; CA-certified turnover (last 5 yrs).
* **Experience PQC:** 1ร—80% / 2ร—50% / 3ร—40% of est. value in past 5 yrs.
* **Docs required:** PAN/GST, EMD, solvency, past SOs/completion certs, ISO 9001, ALMM/OEM certificates.
* **Leh service centre:** Mandatory, with photos + Rent Deed + escalation matrix (non-compliance โ†’ disqualification).
* **Training:** OEM-led, 1 month O&M.

## โš ๏ธ Key Risks

* **High-altitude design challenges:** extreme temperatures, wind, snow.
* **Mandatory IIT/NIT vetting within 30 days** (critical).
* **Strict โ€œMade in Indiaโ€ & ALMM compliance** restricts vendor pool.
* **Service centre at Leh is a hard gate**โ€”must be proven at bid stage.

For more information please see below link: