Summary:
—
# π Project Scope
* **Work:** Provision of **Rooftop Solar Plants (350 kW)** at **Samba Military Station** under GE Samba.
* **Estimated Cost:** βΉ186.00 lakhs (as per market).
* **Completion Period:** **66 months** split in 3 phases:
* **Phase I:** EPC works (BOQ items 1β20) β 3 months.
* **Phase II:** Outsourced O&M (during Defect Liability Period) β 24 months.
* **Phase III:** Outsourced O&M (including comprehensive maintenance) β 36 months.
—
# π° Financials
* **Cost of Tender Documents:** βΉ1,000 (DD/Bankerβs Cheque, in favour of GE Samba).
* **Earnest Money Deposit (EMD):** βΉ2,61,000 (Deposit at Call Receipt in favour of GE Samba; FDR not accepted).
—
# π Timelines
* **Bid Submission Start, Last Date, Opening Date:** As per **critical dates on [defproc.gov.in](https://www.defproc.gov.in)** .
—
# βοΈ Eligibility Criteria
### For MES Enlisted Contractors
* Must be **Class βBβ and above**.
* No adverse remarks in Workload Return.
* Either:
* Be a registered solar vendor on **PM Surya Ghar: Muft Bijli Yojana portal** with required installed capacity, OR
* Have an MoU with such a vendor.
### For Non-Enlisted Contractors
* Must meet **MES Class βBβ enlistment criteria** (work experience with Govt/PSUs, turnover, solvency, working capital).
* No adverse remarks, not blacklisted/debarred.
* Must themselves (or via MoU) be registered on **PM Surya Ghar portal** with required installed capacity.
—
# π§ Technical Pre-Qualification (PQC)
* Must have executed **rooftop solar plants** in Govt/PSUs in last 7 years:
* 1 work β₯ 280 kW, OR
* 2 works β₯ 175 kW, OR
* 3 works β₯ 140 kW.
* βSimilar worksβ = Design, Supply, Installation, Testing & Commissioning of solar plants incl. electrical works.
* Completion certificates + performance reports mandatory.
—
# π₯ Key Authorities
* **Tender Issuing/Accepting Officer:** Chief Engineer, Pathankot Zone (contacts on p.7).
* **Executing Agency:** GE Samba.
—
# π Special Conditions
* **Joint Ventures (JV):** Allowed (max 2 parties). Lead β₯60%, partner β₯30%. Both must meet PQC jointly.
* **Foreign firms:** Not eligible. Indian firms with directors of foreign origin allowed, subject to **MHA clearance**.
* **Subletting:** Not allowed, except to close family/firm staff.
* **Compliance:** GST registration mandatory. Police verification for non-enlisted bidders.
—
# π Implications
* This tender is **strategically tied** to PM Surya Ghar scheme β preference for registered vendors.
* **Long O&M period (5 years total)** adds recurring revenue potential.
* **Strict PQC** ensures only experienced rooftop solar contractors/vendors can qualify.
* JV option opens doors for smaller firms to partner with larger solar vendors.
—