  3. Petition for determination of the transmission tariff from the COD for assets under “Provision of Spare ICT’s” in the Northern Region – EQ
Petition for determination of the transmission tariff from the COD for assets under “Provision of Spare ICT’s” in the Northern Region – EQ

Petition for determination of the transmission tariff from the COD for assets under “Provision of Spare ICT’s” in the Northern Region – EQ

0
0

Summary:

## **Case Summary – Power Grid Corporation of India Ltd. (PGCIL) Transmission Tariff Petitions**

**Forum:** Central Electricity Regulatory Commission (CERC), New Delhi
**Date of Hearing:** 26 August 2025
**Coram:**

* Jishnu Barua, Chairperson
* Ramesh Babu V., Member
* Harish Dudani, Member
* Ravinder Singh Dhillon, Member

### **1. Petitions Covered**

1. **212/TT/2024** – Tariff determination (COD to 31.03.2024) for **7 assets under “Provision of Spare ICTs”** in Northern Region.
2. **284/TT/2024** – Tariff determination (COD to 31.03.2024) for **7 assets under “Scheme to control Fault level (Phase-II)”** in Northern Region.
3. **408/TT/2024** – Tariff determination (COD to 31.03.2024) for **10 assets under “Eastern Region Strengthening Scheme-XVII (Part-B)” (ERSS-XVII Part-B)**.
4. **446/TT/2024** – Tariff determination (COD to 31.03.2024) for **500 MVAr Thyristor Controlled Reactor (TCR) at Kurukshetra**.
5. **59/TT/2025** – Tariff determination (2019–24) for **9 assets under “Strengthening of OPGW network within ER Grid and connectivity with other regions.”**
6. **262/TT/2025** – Tariff determination (2019–24) for **765 kV 80 MVAR Single Phase Reactor at Bilaspur substation** under ERPC/WRPC recommendations.

### **2. Parties**

* **Petitioner:** Power Grid Corporation of India Limited (PGCIL)
* **Respondents:** State DISCOMs/utilities (e.g., UPPCL, BSPHCL, MP Power Management Co. Ltd., etc.).
* **Appearance:** Only BSPHCL appeared (for Petition No. 408/TT/2024).

### **3. Submissions**

* **PGCIL:** Confirmed filing of all requisite information; pleadings complete; requested approval of tariff as claimed.
* **Respondents:** Mostly absent; BSPHCL appeared in one petition.

### **4. Commission’s Directions**

* **General:**

* Last opportunity for Respondents to file replies within **2 weeks** (copy to PGCIL).
* PGCIL may file rejoinder within **2 weeks thereafter**.
* PGCIL to file **additional clarifications by affidavit within 2 weeks**.

* **Petition-specific directions:**

**212/TT/2024:**

* Explain delays in supply of material (Assets 5, 6, 7: delays of 5–21 months).

**284/TT/2024:**

* Provide asset-wise shutdown overrun details (required vs. approved dates).

**408/TT/2024:**

* Submit justification for time overruns (activity-wise, RoW, shutdowns).
* Provide **CEA Energization & Trial-run certificates** for Assets 1A, 5, 8.

**59/TT/2025:**

* Furnish information sought in earlier RoP (20.06.2025).

### **5. Outcome**

* **Type of Order:** Procedural (Record of Proceedings).
* **Effect:** Replies/rejoinders and additional information mandated.
* **Status:** Subject to compliance, Commission **reserved orders** in these petitions.

For more information please see below link: