Petition for determination of transmission tariff for assets under “Upgradation of SCADA/RTUs/SAS in Central Sector Stations and Strengthening of OPGW Network” in the Eastern Region – EQ
Summary:
—
## 📌 Case Overview
* **Petitioner:** Power Grid Corporation of India Ltd. (PGCIL)
* **Respondents:** Bihar State Power (Holding) Company Ltd. & 5 others
* **Subject:** Determination of transmission tariff (2019–24) for assets under *Upgradation of SCADA/RTUs/SAS in Central Sector Stations & Strengthening of OPGW Network* (Eastern Region).
* **Date of Hearing:** 19th August 2025
* **Coram:** Chairperson Jishnu Barua; Members Ramesh Babu V., Harish Dudani, Ravinder Singh Dhillon
—
## ⚡ Proceedings
* On earlier hearing (29.05.2025), PGCIL was allowed to file an **amended petition**.
* Petitioner has since filed the amended petition and requested approval of revised claims.
* BSPHCL appeared through counsel; PGCIL was represented by its officials.
—
## 🏛️ Commission’s Directions
PGCIL directed to file the following, via affidavit, within **two weeks**:
1. **Revised Auditor’s Certificate**, including details of notional IDC.
2. **Liability Flow Statement** of transmission assets.
3. Details of **Liquidated Damages (LD) recovered** during commissioning and adjustments.
4. Confirmation whether **all assets under the scheme are completed** and covered in this petition.
* Respondents to file replies within **2 weeks** (advance copy to PGCIL).
* PGCIL may file rejoinder within **1 week** thereafter.
—
## ✅ Current Status
* Petition has been **reserved for order**, subject to PGCIL filing the required affidavit and respondents’ replies.
* Final tariff order (2019–24) for the Eastern Region SCADA/OPGW upgrade will follow after compliance.
—
For more information please see below link:
Related posts:
- Petition for Truing up and determination of transmission tariff for the “Combined Asset under ERSS-IV” in the Eastern Region – EQ
- Petition for Truing Up and determination of transmission tariff for the Itarsi- Dhule Transmission Line at Khandwa” in the Western Region – EQ
- Petition for determination of transmission tariff with associated bays and equipments at Arasur Sub-station in the Southern Region – EQ
- Petition for determination of the capital cost and transmission tariff at Warangal New Substation Transmission System constructed, maintained and operated – EQ