Petition for Truing up and determination of transmission tariff for the Combined Asset in Northern Region – EQ
Summary:
—
## **Case Summary – PGCIL Transmission Tariff Petitions**
**Forum:** Central Electricity Regulatory Commission (CERC), New Delhi
**Date of Hearing:** 19 August 2025
**Coram:**
* Jishnu Barua, Chairperson
* Ramesh Babu V., Member
* Harish Dudani, Member
* Ravinder Singh Dhillon, Member
—
### **1. Petitions Covered**
1. **385/TT/2025** – *Truing up of transmission tariff (2019–24) and determination of tariff (2024–29)* for the **Combined Asset under Establishment of Fibre Optic Communication System in Northern Region**.
* **Petitioner:** Power Grid Corporation of India Ltd. (PGCIL)
* **Respondents:** Uttar Pradesh Power Corporation Ltd. & 14 others
2. **210/TT/2024** – *Determination of transmission tariff (from DOCO to 31.03.2024)* for assets under the **Transmission System for power evacuation from ARUN-3 (900 MW) HEP, Nepal – Indian Portion**.
* **Petitioner:** PGCIL
* **Respondents:** SJVN Arun-3 Power Development Company Pvt. Ltd. & another
—
### **2. Proceedings**
* **PGCIL submissions:**
* Confirmed petitions filed for tariff truing up/determination.
* Filed additional affidavit (17.06.2025) in Petition 385/TT/2025, as per RoP of 30.05.2025.
* **Respondents:** None appeared, no replies received despite notice.
—
### **3. Commission’s Directions**
* **Petition 385/TT/2025:**
* PGCIL to file an **affidavit within 1 week** with **Excel-linked Form-9C** for all **10 assets**, for both 2019–24 & 2024–29 tariff periods.
* **Both Petitions:**
* Respondents to file replies (affidavit) within **1 week** (copy to PGCIL).
* PGCIL may file rejoinders within **1 week thereafter**.
—
### **4. Outcome**
* **Type of Order:** Procedural (RoP).
* **Effect:** Procedural compliances directed; Excel tariff forms required; Respondents’ replies awaited.
* **Status:** Subject to compliance, **orders reserved** in both petitions.
—