Petition for Truing up and the determination of transmission tariff for Palatana-Bongaigaon Transmission System Project in the North Eastern Region – EQ

Petition for Truing up and the determination of transmission tariff for Palatana-Bongaigaon Transmission System Project in the North Eastern Region – EQ

0
0

Summary:

**Subject of the Petition**

North East Transmission Company Limited (NETC) has filed a petition seeking:
1. **Truing up** of the transmission tariff for the tariff period **2019–24**.
2. **Determination** of the transmission tariff for the tariff period **2024–29** for assets under the **400 kV Palatana–Bongaigaon Transmission System Project** in the North Eastern Region.

**Petitioner’s Submissions**

– NETC submitted detailed breakup of **actual O&M (Operation & Maintenance) Expenses** for 2019–24, along with supporting documents.
– Also filed: **add-cap details, audited balance sheets, and TCC (Technical Coordination Committee) meeting minutes**.
– Requested the Commission to **exercise its Power to Relax** and approve the claimed O&M Expenses for both tariff periods.

**Commission’s Observations & Directions**

The Commission noted that the Petitioner had **not fully complied** with earlier directions issued in the hearing dated **August 19, 2025**.

**Directions Issued (to be complied within two weeks):**

1. **Head-wise details** of the actual **Annual Capital Expenditure (ACE)** incurred during 2019–24.
2. **Supporting documents/Court order** for compensation of **₹59.45 lakh** paid by NETC.
3. **Liability Flow Statement** for both tariff periods (2019–24 and 2024–29).
4. **Assessment of Security requirement** for the 2024–29 tariff period.

For more information please see below link: