1. Home
  2. Featured
  3. Petition of SSDGCT seeking directions to MSEDCL for facilitating net metering to its installation and refund of monies charged by billing under gross metering modality along with applicable interest – EQ
Petition of SSDGCT seeking directions to MSEDCL for facilitating net metering to its installation and refund of monies charged by billing under gross metering modality along with applicable interest – EQ

Petition of SSDGCT seeking directions to MSEDCL for facilitating net metering to its installation and refund of monies charged by billing under gross metering modality along with applicable interest – EQ

0
0

Summary:

MERC – Case No. 219 of 2024 (SSDGCT vs. MSEDCL)**

## **1. Case Overview**

* Sou Sushila D. Ghodawat Charitable Trust (SSDGCT) filed a petition seeking:

* Net metering benefit during periods when Open Access (OA) was availed.
* Refund of **₹60.96 lakh** overcharged due to gross metering.
* Action under Section 142 for deliberate violation of DOA Regulations.

## **2. SSDGCT’s Key Facts & Claims**

* Consumer with 1050 kVA demand, rooftop solar of **748.8 kWp**, and partial OA from a 1.25 MW wind generator.
* Net metering was **approved in 2019** and implemented from July 2020 to Dec 2023.
* From Jan, Feb, Mar, Aug, Sept, Oct 2024 – **MSEDCL unilaterally shifted to gross metering** while OA was active.
* This caused large financial losses; net metering benefits were granted only in Apr–Jul 2024.
* No notice or justification was provided by MSEDCL.
* SSDGCT claims MSEDCL cannot deny net metering because of its own failure to implement DOA Amendment procedures in time.

## **3. MSEDCL’s Response**

* Argues SSDGCT’s OA applications were **not valid** under the DOA Second Amendment Regulations & GEOA Rules 2022.
* Claims Open Access was to be sought through MSLDC, not MSEDCL.
* States Regulation 3.4 is ambiguous, so gross metering was used.
* Asserts any error was unintentional and due to regulatory uncertainty.
* Refers to Case No. 232/2024 (its clarificatory petition) still pending before MERC.

## **4. SSDGCT’s Rejoinder**

* No regulation allows MSEDCL to change a net-metered system to gross metering.
* MSEDCL delayed implementing DOA 2023 by **10 months**, causing confusion for all consumers.
* MSEDCL issued STOA approvals themselves—therefore **cannot claim them invalid later**.
* SSDGCT cannot be penalized for MSEDCL’s failure to communicate process changes.
* Doctrine: *“No one can benefit from their own wrong.”*

## **5. Key Regulatory Interpretation by MERC**

### **a) Net Metering + Open Access is Allowed Post DOA Amendment 2023**

* DOA 2023 deleted the Gross Metering requirement for OA periods.
* Regulation 3.4 expressly permits **simultaneous rooftop net metering and OA**.

### **b) MSEDCL’s Delay Caused Compliance Issues**

* Circular implementing DOA 2023 issued **10 months late** (Sept 2024).
* This delay directly contributed to SSDGCT’s procedural missteps.

### **c) MSEDCL Issued OA Approvals**

* Since MSEDCL approved STOA for the months under dispute, they cannot later claim invalidity.
* Therefore, **net metering benefits cannot be denied**.

## **6. Precedent Case Applied**

* MERC refers to its own **Order dated 28 July 2025 in Case No. 197 of 2024**, where MSEDCL agreed to credit solar generation under net metering for a similar situation.
* MERC states **similar consumers must be treated alike**.

## **7. MERC’s Findings**

* SSDGCT is entitled to **net metering benefit** for all disputed months in 2024.
* Denial of net metering occurred due to MSEDCL’s own delay in implementing regulations.
* MSEDCL **cannot use regulatory ambiguity as a defense** for overbilling.
* Consumer should not suffer due to utility’s delay or unclear procedures.

## **8. Refund & Reconciliation**

* SSDGCT claimed ₹60.96 lakh refund but did not provide a detailed computation.
* MSEDCL also did not present calculations.
* MERC directs both parties to:

* **Reconcile the amount within 30 days**.
* Apply refund/credit in the very next billing cycle.
* Add interest at the **Bank Rate**.

## **9. Final Order**

1. **Petition Allowed** in favour of SSDGCT.
2. MSEDCL must:

* Reconcile and credit the refund amount within 30 days.
* Apply net-metering-based adjustments for all disputed months.
* Reflect reconciled credit in the next billing cycle.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network