In the matter of: Petition under Section 79(1)(c) and (k) of the Electricity Act, 2003 read with Regulation 34(1) and Regulation 37 of the Central Electricity Regulatory Commission (CrossBorder Trade of Electricity) Regulations, 2019 for declaration that revocation of the Letter of Intent dated 3.1.2020 issued to the Petitioner is illegal and arbitrary and further […]
IN THE MATTER OF: Implementation of the directions of the Government of India dated 28.03.2020 under section 107 of the Electricity Act, 2003 to Central Electricity Regulatory Commission regarding reduction of Late Payment Surcharge For more information please see below link:
In the letter on Monday, the ministry said late payment surcharge is applicable in case of nonpayment of dues within the stipulated period. This surcharge in most cases goes up to 18 per cent per year NEW DELHI: With its relief being construed as a moratorium on payments, the Union power ministry has clarified that […]
In the matter of: Approval of transmission tariff for Asset I – STATCOM System (+/-) 300 MVAR complete in all respect including Coupling transformer, Mechanically switched compensation (2×125 MVAR reactor), cooling system & STATCOM protection/ controller etc. at Ranchi Substation and Asset II – STATCOM System (+/-) 200 MVAR complete in all respect including Coupling […]
In the matter of: Approval under Regulation-86 of CERC (Conduct of Business) Regulations, 1999 and CERC (Terms and Conditions of Tariff) Regulations, 2014 for determination of Transmission tariff from COD to 31.3.2019 for Asset-1: Replacement of existing 1 no.50 MVA, 220/132 kV ICTs by 160 MVA, 220/132 kV ICT at Balipara Sub-station along with replacement […]
In the matter of: Petition under Section 79(1)(f) of the Electricity Act, 2003 for claiming compensation on account of occurrence of ‘Change in Law’ events as per Article 10.1.1 of the Case-1 long-term Power Purchase Agreement dated 27.11.2013 read with Addendum No.1 dated 20.12.2013 entered into between Dhariwal Infrastructure Limited and Tamil Nadu Generation and […]
DSM 5th amendment which was scheduled to be applied w.e.f 01st April 2020 is rescheduled to be applied w.e.f 01st June 2020 due to COVID-19 outbreak For more information please see below link:
IN THE MATTER OF: Extension of the period of applicability of the levellised generic tariff for RE issued vide order dated 19.03.2019 in Petition No. 01/SM/2019 For more information please see below link: CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 3/SM/2020 (Suo-Motu) Coram: 1. Shri P.K. Pujari, Chairperson 2. Shri I. S. Jha, Member […]
In the matter of: Application under Sections 14, 15 and 79(1)(e) of the Electricity Act, 2003 read with Central Electricity Regulatory Commission (Procedure, Terms and Conditions for Grant of Transmission Licence and other related matters) Regulations, 2009 with respect to grant of Transmission Licence to Jam Khambaliya Transco Limited For more information please see below […]