1. Home
  2. Tag "CERC"

Petition with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations for Rajgarh Neemuch Power Transmission Ltd – EQ

Summary: — ## 1. PETITION OVERVIEW **Purpose**: Petition filed under **Sections 14, 15, and 79(1)(e) of the Electricity Act, 2003**, read with **CERC Transmission Licence Regulations, 2024**, seeking grant of **inter-State transmission licence** for: **Project Name**: *”Evacuation of Power from RE Projects in Rajgarh (1500 MW) SEZ in Madhya Pradesh – Phase III”* and *”Evacuation […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Truing up and determination of the transmission tariff for Central Part of Northern Grid Part-I – EQ

Summary: — ## 1. PETITION OVERVIEW **Purpose**: 1. **Truing-up** of transmission tariff for **2019-24 period** (2019 Tariff Regulations) 2. **Determination** of transmission tariff for **2024-29 period** (2024 Tariff Regulations) **Assets Covered**: Combined Assets under *”765 kV System for Central Part of Northern Grid Part-I”* | **Asset No.** | **Description** | **COD** | |————–|—————-|———| | Asset-1 […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

In the matter of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Truing up and determination for “Transmission System associated with SEWA-II HEP” in the Northern Region – EQ

Summary: — ## 1. **Transmission Assets Overview** | **Asset** | **Description** | **COD** | **Remarks** | |———-|—————–|——–|————-| | **Asset-I** | One circuit of 132 kV D/C SEWA-II Hiranagar line along with associated bays at Hiranagar Sub-station and one circuit of 132 kV D/C SEWA-II Mahanpur line and associated bays at Mahanpur | 01.09.2009 | Notional […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

In the matter of Approval of CERC (Conduct of Business) Regulations for the truing up and determination of Transmission Tariff for ECEPL and NCC Power Projects Ltd generation projects in Srikakulam Area-Part-C – EQ

Summary: — ## 1. **Project Cost & Investment Approvals** | **Parameter** | **Details** | |————–|————-| | **Original Investment Approval** | 28.03.2013 (BoD 285th Meeting) | | **Original Estimated Cost** | ₹51,420 lakh (including IDC ₹2,879 lakh) – Feb 2013 PL | | **Revised Cost Estimate (RCE)** | 29.03.2017 (BoD 339th Meeting) | | **RCE Estimated […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition for Adoption of ISTS Grid connected Solar Power projects of 1200 MW with Energy storage system (ESS) with “Greenshoe Option” (NHPC Tranche -VIII) – EQ

Summary: — ## 1. **Petition Overview & Relief Sought** NHPC filed this petition under **Section 63 of the Electricity Act, 2003** seeking: | **Prayer** | **Details** | |———–|————| | **Tariff Adoption** | Adoption of tariff discovered through competitive bidding for 1200 MW ISTS-connected Solar PV projects with 600 MW / 1200 MWh ESS | | […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

In the matter of Adoption of transmission charges with Transmission System by the POWERGRID Kudankutam Transmission Ltd (a 100% wholly owned subsidiary of Power Grid Corporation of India Ltd) – EQ

Summary: — ### **SUBJECT OF PETITION** – Application under **Section 63 of the Electricity Act, 2003** for **adoption of transmission charges** discovered through competitive bidding for the **Inter-State Transmission System (ISTS)** for evacuation of power from **Kudankulam Unit 3 & 4 (2×1000 MW)** on a **Build, Own, Operate, Transfer (BOOT)** basis. — ### **KEY FINDINGS […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to KPS III HVDC Transmission Ltd – EQ

Summary: — ### **HEARING & PROCEEDINGS** – **Date of Hearing:** 21.01.2026 – **Bench:** Chairperson Shri Jishnu Barua, Members Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon – **Key Submission:** AESL filed petitions for transmission license grant and tariff adoption for the Khavda RE evacuation project. – **Commission’s Query:** Why petitions filed by […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition for Adoption of tariff for 2000 MW ISTS Solar PV Power Projects with ESS and SECI-ISTS-XX of the Government of India – EQ

Summary: — ### **PETITION DETAILS** – **Petitioner:** Solar Energy Corporation of India Limited (SECI) – **Respondents:** Welspun Renewable Energy Private Limited & Others – **Subject:** Petition under **Section 63 of the Electricity Act, 2003** for adoption of tariff for **2000 MW Inter-State Transmission System (ISTS) Solar PV Power Projects** with **1000 MW / 4000 MWh […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition for truing up and determination of the transmission tariff for Transmission Line along with extension of Raipur and Rourkela Sub-stations under Eastern-Western inter-regional link” in the Western Region – EQ

Summary: — ### **Subject of the Petition** PGCIL has filed a petition for: 1. **Truing up of transmission tariff** for the **2019–24 tariff period**. 2. **Determination of transmission tariff** for the **2024–29 tariff period**. **Project**: > **Asset-1**: 400 kV Raipur–Rourkela Double Circuit (D/C) Transmission Line, along with extension of Raipur and Rourkela substations under the […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ

Petition of the CERC (Conduct of Business) and (Terms and Condition of Tariff) Regulations for determination and Installation of OPGW on existing Koldam – Ludhiana (PG) – EQ

Summary: — ### **Subject of the Petition** PKTCL has filed a petition seeking determination of the **transmission tariff** for the period from the **Commercial Operation Date (COD)** to **31 March 2029** for the following project: > **Project**: Supply and Installation of OPGW (Optical Ground Wire) on the existing 400 kV Koldam–Ludhiana (PG) line, which is […]

Petition for Adoption of tariff of 1500 MW Solar PV Power Projects Connected to the ISTS of the Ministry of Power, Government of India as amended from time to time – EQ