Petition for Truing up and determination of transmission tariff for “SYSTEM STRENGTHENING–XX” in the Southern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) – EQ

Summary: — ### **1. Introduction & Case Overview** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Subject:** Petition for truing up of transmission tariff for the period **2019–24** and determination of transmission tariff for the period **2024–29** for **Combined Assets** under the “System Strengthening–XX” scheme in the Southern Region. – **Legal Basis:** Electricity […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

Petition for determination of tariff for the asset under “Eastern Region Expansion Scheme – XXVIII (ERES-XXVIII)” of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Summary: — ### **Regulatory Context** * The Central Electricity Regulatory Commission (CERC) heard **five transmission tariff petitions** filed by **Power Grid Corporation of India Ltd. (PGCIL)**. * Proceedings relate to **tariff determination and truing-up** under **Section 62 of the Electricity Act, 2003**. * Applicable tariff regulations include **CERC Tariff Regulations, 2019 and 2024**. * **Date […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

In the matter of Approval of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of transmission tariff for “Combined asset under URI- II HEP Transmission System” in the Northern Region – EQ

Summary: — ### **1. Regulatory Outcome** * CERC has **approved truing-up of transmission tariff for FY 2019-24** and **determined tariff for FY 2024-29**. * Applicable to **Combined Asset under URI-II HEP Transmission System** in the **Northern Region**. * Order dated **5 December 2025**. — ### **2. Project & Asset Overview** * **Asset Owner:** Power Grid […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Gazuwaka under “Gazuwaka HVDC back to back project” in the Southern Region – EQ

Summary: — **Subject of the Petition** Power Grid Corporation of India Limited (PGCIL) has filed a petition under: – **Section 62 read with Section 79(1)(d) of the Electricity Act, 2003** – **Regulations 15(1)(a) and 23 of the CERC (Conduct of Business) Regulations, 2023** – Read with the **CERC (Terms and Conditions of Tariff) Regulations, 2019 […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

CSERC (Conduct of Business) (Second Amendment) Regulations, 2025 – EQ

Summary: — **1. Key Document Details** * **Issuing Authority:** Chhattisgarh State Electricity Regulatory Commission (CSERC) * **Notification No.:** 113/CSERC/2025 * **Date of Notification:** 20th November 2025 * **Legal Basis:** Issued under **Section 181 of the Electricity Act, 2003**. * **Subject:** Amendment to the **CSERC (Conduct of Business) Regulations, 2009**. **2. Purpose & Context** The amendment […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

In the Matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations under System Strengthening Scheme in Northern Region–XXXVII (NRSS-XXXVII) – EQ

Summary: — **Key Dates & Delays** – **Asset-1:** SCOD – 19.12.2019, COD – 4.12.2022 → **Time overrun: 1081 days** – **Asset-2:** COD claimed as 5.1.2023 → Delay due to unready downstream asset by PTCUL. – **Asset-3:** COD claimed as 5.1.2023 → Delay due to washed-out bridge preventing reactor relocation. **PGCIL’s Claims** – **Asset-2:** COD claimed […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

In the matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for determination of transmission tariff from COD under TSA with Mundra Ultra Mega Power Project – EQ

Summary: — # **1. Scope of Work** The bidder must execute the *complete* EPC + long-term O&M responsibility for: ### **🔹 10 MW Rooftop Solar PV System (Jodhpur District)** * Installation on multiple State Government office buildings, institutional buildings, and other public structures. * Project includes design, engineering, supply, installation, net-metering, commissioning, and maintenance for […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

Petition for Truing up and determination of the transmission tariff of the CERC (Conduct of Business) ans (Terms and Conditions of Tariff) Regulations for Phase-II generation projects in Odisha” in the Eastern region – EQ

Summary: — ## **1. Nature of the Petition** The petition has been filed by **Power Grid Corporation of India Limited (PGCIL)** seeking: 1. **Truing-up** of transmission tariff for the period **2019–24**. 2. **Determination of tariff** for the next control period **2024–29**. The assets involved belong to the **“Common Transmission System for Phase-II Generation Projects in […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) under “Gazuwaka HVDC back to back project” in the Southern Region – EQ

Summary: — ## 📋 **Case Overview** – **Petition No.**: 495/TT/2025 – **Petitioner**: Power Grid Corporation of India Limited (PGCIL) – **Subject**: – Truing up of transmission tariff for **2019–24** – Determination of transmission tariff for **2024–29** – Assets involved: – **Asset-1**: 400 kV Joypore-Gazuwaka transmission line with bays – **Asset-2**: 500 MW HVDC back-to-back stations […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ

Petition of the CERC (Conduct of Business) Regulations for review of the Order – EQ

Summary: —- **Parties:** – **Petitioner:** Power Grid Corporation of India Limited (POWERGRID) – **Respondents:** Bihar State Power Holding Company Limited (BSPHCL) and 5 Others **Subject:** Review Petition filed under **Section 94(1)(f) of the Electricity Act, 2003** read with **Regulation 52 of CERC (Conduct of Business) Regulations, 2023**, seeking review of the **Order dated 13.6.2025** passed […]

CSERC (Terms and conditions for determination of tariff for Renewable Energy sources) Regulations, 2025 – EQ