Petition for Truing up and determination of transmission tariff of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations 2019 & 2024 – EQ

Summary: — ### **Case Information** – **Petition No.**: 412/TT/2025 – **Subject**: Petition for truing up of transmission tariff for the **2019–24 period** and determination of transmission tariff for the **2024–29 period** for the Combined Transmission System associated with the **Kaiga 3 & 4 (2×235 MW) Project** in the Southern Region. – **Petitioner**: Power Grid Corporation […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for the determination for Transmission System Strengthening Scheme for Evacuation of Power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-II-Part-A1 in the Northern Region – EQ

Summary: — ### **1. Regulatory Authority** * Central Electricity Regulatory Commission (CERC), New Delhi. * Proceedings conducted under the Electricity Act, 2003 and applicable CERC Tariff Regulations. ### **2. Petition Overview** * Filed by **Power Grid Corporation of India Limited (PGCIL)**. * Petition relates to determination of **transmission tariff for the 2024–29 tariff period**. * […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition of the CERC (Terms and Conditions of Tariff) for Truing-up and determination of tariff for Srinagar- Srinagar PH Line (Deemed ISTS) under UITP Scheme- EQ

Summary: — ### **1. Regulatory Authority** * Central Electricity Regulatory Commission (CERC), New Delhi. * Proceedings conducted under the Electricity Act, 2003 and applicable CERC Tariff Regulations, 2014 and 2019. ### **2. Petition Overview** * Filed by **Power Transmission Corporation of Uttarakhand Limited (PTCUL)**. * Relates to the **400 kV Srinagar–Srinagar PH Transmission Line** classified […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for truing up and the determination of transmission tariff for Coastal Energen Private Limited and Ind-Bharat Power (Madras) Limited LTOA Generation Projects in Southern Region – EQ

Summary: — ## 📄 **Case Details** – **Petition No.**: 606/TT/2025 – **Petitioner**: Power Grid Corporation of India Limited (PGCIL) – **Respondents**: Tamil Nadu Generation and Distribution Corporation (TANGEDCO) and 15 Others – **Date of Hearing**: 11.12.2025 – **Bench**: Shri Ramesh Babu V. (Member), Shri Harish Dudani (Member) — ## 🧾 **Subject of Petition** PGCIL filed […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for determination of Transmission System for Transfer of Power from generation projects in the Eastern Region – EQ

Summary: — ## 📄 **Case Details** – **Petition No.**: 337/TT/2022 – **Petitioner**: Power Grid Corporation of India Limited (PGCIL) – **Respondents**: Bihar State Power (Holding) Company Limited (BSPHCL) and Others – **Date of Hearing**: 11.12.2025 – **Bench**: Shri Ramesh Babu V. (Member), Shri Harish Dudani (Member) — ## 🧾 **Subject of Petition** PGCIL sought approval […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for the determination of transmission tariff for asset under ‘Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Summary: —- Document 1: CERC Hearing Proceedings (875/TT/2025) Key Proceedings: Petitioner’s Submission: PGCIL filed for tariff determination for the 2024-29 period. MSEDCL’s Request: Respondent No. 2 (MSEDCL) sought 4 weeks to file a reply. Commission’s Directions: PGCIL to implead CTUIL as a party and file a revised memo within a week. Issue notice to all […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for Truing up and determination of the transmission tariff for Combined Asset under “North Eastern Region Strengthening Scheme-IV” in the North Eastern Region – EQ

Summary: — ### **1. Case Details** – **Hearing Date**: 27.11.2025 – **Bench**: Shri Ramesh Babu V. (Member) and Shri Harish Dudani (Member) – **Petitioner**: **Power Grid Corporation of India Limited (PGCIL)** – **Respondents**: Various state power distribution/management companies (e.g., MPPMCL, APDCL, etc.) — ### **2. Petitions Involved** Five separate petitions were heard together: | Petition […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for determination of the Transmission Tariff for the Transmission Assets under Transmission System Strengthening Scheme for evacuation of power from Solar Energy Zones in RJ – EQ

Summary: — ### **1. Case Details** – **Petition No.**: 80/TT/2025 – **Subject**: Determination of **Transmission Tariff** for assets under the **Transmission System Strengthening Scheme for evacuation of power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-II-Part B1**. – **Petitioner**: **Power Grid Corporation of India Limited (PGCIL)** – **Respondents**: **Ajmer Vidyut Vitran Nigam Limited […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for determination of transmission tariff for 2014-19 tariff period – EQ

Summary: —- **BACKGROUND:** – **Remand Order:** Appellate Tribunal for Electricity (APTEL) remanded back CERC’s earlier order dated 29.6.2018. – **Reason for Remand:** APTEL directed re-determination of tariff based on: 1. Actual capital cost 2. Legitimate weighted average interest on loan (WAROI) 3. Grossed-up return on equity based on true effective tax rates 4. Correct useful […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ

Petition for Truing up and determination of the transmission tariff for Double Circuit Purnea-Muzaffarpur and Muzaffarpur (PGCIL)-Muzaffarpur (BSEB) Transmission Line, in the Eastern Region and the Northern Region associated with Tala HEP of Powerlinks Transmission Limited – EQ

Summary: —- **KEY POINTS OF PROCEEDINGS:** 1. **Interim Application (IA 97/2025) – Allowed** • Petitioner’s application for amendment of prayers in Petition granted. • Amended petition taken on record; IA disposed of. 2. **Directions to Respondents** • Respondents granted **final opportunity** to file replies within **7 days** (copy to Petitioner). • Petitioner may file rejoinder […]

Draft KERC (Roadmap for Reducing Cross-Subsidy and Cross Subsidy Surcharge) Regulations, 2025 – EQ