Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Summary: —- **1. Document Nature & Core Issue:** * This is a consolidated **regulatory proceeding record** from the **Central Electricity Regulatory Commission (CERC)**, covering two related tariff petitions filed by the Power Grid Corporation of India Limited (PGCIL). * **Petitions Involved:** * **Petition No. 602/TT/2025:** For determination of tariff for the **2024-29 period** for Combined […]

Petition for the determination of the tariff for RRVPN-owned transmission lines/system connecting to inter-State transmission of electricity for inclusion in the POC transmission charges – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for determination of transmission tariff for HPPTCL – EQ

Summary: — ### **1. PETITION OVERVIEW** * **Petitioner:** Himachal Pradesh Power Transmission Corporation Limited (HPPTCL) * **Respondents:** Himachal Pradesh State Electricity Board Limited (HPSEBL) and Others * **Subject:** A petition filed under the **Electricity Act, 2003** and relevant CERC regulations for: 1. **Truing up** of the transmission tariff for the **2019-24** period (adjusting past tariffs […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Truing up and determination of the transmission tariff for Combined Asset under “Northern Region System Strengthening Scheme-XV” – EQ

Summary: — ### **1. PROCEEDINGS & COMMISSION’S DIRECTIONS** After hearing PGCIL’s representatives, the Commission issued the following procedural directions: **A. Timeline for Submissions:** 1. **Respondents** (State Utilities) to file their **replies within two weeks**, with an advance copy to PGCIL. 2. **PGCIL** may file its **rejoinder within two weeks** thereafter. **B. Specific Information Sought from […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Truing up and determination of transmission tariff for the Combined Asset under “Integration of Pooling Stations in Chhattisgarh with Central Part of the Western Region for IPP Generation Projects – EQ

Summary: —- ### **1. Overview and Context:** – **Date of Hearing:** 13th January 2026. – **Common Petitioner:** Power Grid Corporation of India Limited (PGCIL). – **Subject:** Multiple petitions (listed below) for **truing up of tariffs for the 2019-24 period** and **determination of tariffs for the 2024-29 period** for various transmission assets across India. – **Regulatory […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Truing up and determination of the transmission tariff for “Transmission System of Vindhyachal-IV & Rihand-III (1000 MW) Generation Project” in the Western Region – EQ

Summary: — **1. Overview of Petitions** All three petitions filed by **Power Grid Corporation of India Limited (PGCIL)** seek: – **Truing up** of transmission tariff for the period **2019–24**. – **Determination** of transmission tariff for the period **2024–29**. **2. Petition-wise Summary** | Petition No. | Scheme / Asset Description | Region | Key Respondents | […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Truing up and determination of transmission tariff for “Integration of Pooling Stations with Central Part of the Western Region for IPP Generation Projects in Chhattisgarh” – EQ

v Sumamry: — **1. Regulatory Authority** Central Electricity Regulatory Commission (CERC), New Delhi. **2. Overview of Petitions** A **combined proceeding** covering **11 separate tariff petitions** filed by **Power Grid Corporation of India Limited (PGCIL)** for truing up of transmission tariffs for the period **2019–24** and determination of tariffs for **2024–29**. **3. Common Objective Across All […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for the determination of transmission tariff for “Transmission Network Expansion in Gujarat to increase ATC from ISTS, Part-B” in the Western Region – EQ

Summary: — ### **1. Nature of the Petition** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Respondents:** Madhya Pradesh Power Management Company Limited (MPPMCL) and 6 Others (including MSEDCL) – **Subject:** Determination of **transmission tariff for the 2024–29 tariff period** for assets under the project **”Transmission Network Expansion in Gujarat to increase ATC […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Truing up and determination of transmission tariff for Bawana – Mandaula Double Ckt. and Bamnauli – Ballabhgarh Double Ckt. transmission lines as CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Summary: — ### **1. Overview & Context** * **Document Type:** CERC Order/Proceeding from a hearing held on **13 January 2026**. * **Core Subject:** Hearing for two interconnected tariff petitions filed by **Delhi Transco Limited (DTL)**, concerning the same set of critical 400 kV transmission lines in the Delhi region. * **Legal Framework:** Petitions filed under […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for True up of tariff and determination of Annual Revenue Requirement for FY 2024-25 – EQ

Summary: — ### **1. PARTIES PRESENT** – **Representative of DTL (Petitioner):** Mr. Deepak Soni, DGM (C&RA) Division. — ### **2. KEY SUBMISSIONS BY DTL** 1. **Accounts for FY 2022-23** will be filed with the Commission **within 7 days**. 2. Due to **administrative reasons**, the accounts will be submitted **provisionally**—without an audited report. 3. The accounts […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ

Petition for Adoption of tariff for purchase of power up to 200 MW of the DERC (Terms and Conditions for Determination of Tariff Regulations – EQ

Summary: — #### **1. Purpose** EPIL is inviting **Expressions of Interest (EOI)** from experienced and reputable Indian contractors/firms for **empanelment as potential partners** for upcoming **Solar PV Power Plant projects** on an **Engineering, Procurement, and Construction (EPC)** basis. The empanelment is for the following partnership models: – **Joint Venture (JV) Partner** – **Consortium Partner** – […]

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff with Tehri Transmission System in the Northern Region – EQ