Petition of the GERC (Conduct of Business) Regulations of the Evacuation Line along with bays and metering system of the 4.15 MW Solar – Wind Hybrid Project – EQ

Summary: — # ⚖️ Case Details * **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar. * **Petition No.:** 2438 of 2025. * **Filed under:** Section 86 of the Electricity Act, 2003 + GERC Conduct of Business Regulations, 2004. * **Policy basis:** Gujarat Renewable Energy Policy, 2023 + Tariff Order dated 31.08.2024. * **Subject:** Request for extension […]

Petition for the Adoption for procurement of power from the 760 MW Grid Connected Renewable Energy Power Projects with Energy Storage Systems – EQ

Petition of the GERC (Conduct of Business) Regulations for commissioning of the Evacuation Line and metering system of the 4.15 MW Solar – Wind Hybrid Project – EQ

Summary: — ## **Durga Processors Pvt. Ltd. vs. GETCO & Ors.** **Forum:** Gujarat Electricity Regulatory Commission (GERC), Gandhinagar **Petition No.:** 2438 of 2025 **Order Date:** 02 August 2025 **Coram:** * Mehul M. Gandhi, Member * S.R. Pandey, Member — ### **1. Case Background** * **Petitioner:** Durga Processors Pvt. Ltd., Surat * Counsel: Ld. Adv. M.N. […]

Petition for the Adoption for procurement of power from the 760 MW Grid Connected Renewable Energy Power Projects with Energy Storage Systems – EQ