Summary: —- **KEY PROCEEDINGS:** 1. **Name Change of Petitioner:** – Petitioner’s representative informed the Commission that the process of changing the company’s name is ongoing. – Requested permission to file an affidavit with supporting documents regarding the name change. 2. **Commission’s Direction:** – Petitioner permitted to file an affidavit within **one week**, placing on record […]
Summary: —- **BACKGROUND:** – **Remand Order:** Appellate Tribunal for Electricity (APTEL) remanded back CERC’s earlier order dated 29.6.2018. – **Reason for Remand:** APTEL directed re-determination of tariff based on: 1. Actual capital cost 2. Legitimate weighted average interest on loan (WAROI) 3. Grossed-up return on equity based on true effective tax rates 4. Correct useful […]
Summary: —- **KEY POINTS OF PROCEEDINGS:** 1. **Interim Application (IA 97/2025) – Allowed** • Petitioner’s application for amendment of prayers in Petition granted. • Amended petition taken on record; IA disposed of. 2. **Directions to Respondents** • Respondents granted **final opportunity** to file replies within **7 days** (copy to Petitioner). • Petitioner may file rejoinder […]
Summary: — 1. **Scope & Eligibility**: * Applies to RE projects achieving Commercial Operation Date (COD) between **1st April 2025 and 31st March 2030**, located within the state, and supplying their entire power to state distribution licensees on a long-term basis. * Defines eligibility criteria for various technologies: Wind, Small Hydro, Solar (PV, Thermal, Floating), […]
Summary: —- **1. Scope of Application:** The Regulations apply to the following entities operating in Chhattisgarh: * State Transmission Utility * Generating companies (supplying power to distribution licensees in the state under long-term agreements, except stations under central jurisdiction and certain renewable energy stations) * All intra-state transmission licensees * All distribution licensees * State […]
Summary: — ## **PART 1: INTRODUCTION & SCOPE** ### **1.1 Legal Basis & Commencement** * **Enacted under:** Sections 61, 62, 181(2), and 32(3) of the Electricity Act, 2003. * **Control Period:** April 1, 2026, to March 31, 2030. * **Applicability:** Extends to the entire state of Chhattisgarh. ### **1.2 Regulated Entities** The regulations apply to: […]
Summary: — ### **1. Background** * The matter relates to a petition filed before the **Central Electricity Regulatory Commission (CERC)** by **Delhi Transco Limited (DTL)**. * The petition seeks **truing-up of transmission tariff for the 2019–24 control period** and **determination of tariff for the 2024–29 period**. * The assets involved are: * **400 kV Bawana […]
Summary: — ### **Regulatory Context** * The Central Electricity Regulatory Commission (CERC) heard **five transmission tariff petitions** filed by **Power Grid Corporation of India Ltd. (PGCIL)**. * Proceedings relate to **tariff determination and truing-up** under **Section 62 of the Electricity Act, 2003**. * Applicable tariff regulations include **CERC Tariff Regulations, 2019 and 2024**. * **Date […]
Summary: — ### **1. Regulatory Outcome** * CERC has **approved truing-up of transmission tariff for FY 2019-24** and **determined tariff for FY 2024-29**. * Applicable to **Combined Asset under URI-II HEP Transmission System** in the **Northern Region**. * Order dated **5 December 2025**. — ### **2. Project & Asset Overview** * **Asset Owner:** Power Grid […]