Petition with the CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to SR WR Power Transmission Limited – EQ

Summary: — ### 1. Project Overview The project, titled **”Inter-Regional Strengthening between SR Grid and WR Grid,”** is a critical transmission scheme aimed at enhancing power transfer capability and facilitating the evacuation of renewable energy (RE) from the Southern Region. – **Project Scope (The “Project”):** – **Parli New (WR) – Bidar (SR) 765 kV D/C […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations for Transmission system for providing connectivity at Navinal (Mundra)(GIS) under RTM route – EQ

Summary: —- **1. Overview of the Petition** – **Petition No:** 1029/TL/2025 – **Subject:** Application for the grant of a separate transmission license. – **Petitioner:** Navinal Transmission Limited (NNTL). – **Purpose:** To obtain a transmission license for a system at Navinal (Mundra) (GIS) under the Regulated Tariff Mechanism (RTM) route. This system is intended to provide […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

In the matter of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations at Tuticorin-II GIS in the Southern Region – EQ

Summary: —- **1. Overview of the Petition** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL). – **Purpose:** 1. **Truing-up** of Annual Fixed Charges (AFC) for the 2019-24 tariff period (based on 2019 Tariff Regulations). 2. **Determination** of AFC for the 2024-29 tariff period (based on 2024 Tariff Regulations). – **Asset in Question:** – **Asset […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

In the matter of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations with bays at Wardha under “Mauda Transmission System” in the Western Region – EQ

Summary: —- **1. Overview of the Petition** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL). – **Purpose:** 1. **Truing-up** of Annual Fixed Charges (AFC) for the 2019-24 tariff period (based on 2019 Tariff Regulations). 2. **Determination** of AFC for the 2024-29 tariff period (based on 2024 Tariff Regulations). – **Asset in Question (Combined Asset):** […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to NERGS-I Power Transmission Ltd – EQ

Summary: —- **Key Procedural Development:** – **Withdrawal Petition:** The Petitioner (NREGSPTL) has now filed an Interlocutory Application (IA) – **IA (Diary) No.34/2026** – seeking permission to **withdraw** the main transmission license petition (No. 322/TL/2024). – **Objective of Withdrawal:** The Petitioner seeks liberty to file a **fresh petition** at a subsequent date. This suggests a need […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition for Adoption of 6000 MWh Peak Power from ISTS- connected Renewable Energy Power Projects with Energy Storage System anywhere in India – EQ

Summary: —- **Key Regulatory Developments:** 1. **Compliance with Previous Orders:** SJVNL informed the Commission that it has complied with directions from the January 21, 2026 hearing. It filed an affidavit on February 4, 2026, providing details regarding the competitiveness of the discovered tariff. 2. **Power Sale Agreement (PSA) Progress:** – SJVNL has entered into a […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to KPS III HVDC Transmission Ltd – EQ

Summary: —- **Key Legal & Procedural Developments:** 1. **Compliance with Previous Orders:** ATL informed the Commission that it has complied with directions issued on January 21, 2026, by: – Impleading **KPS III HVDC Transmission Limited** as a co-petitioner. – Adding **Powergrid KPS3 Transmission Limited** and **South Olpad Transmission Limited** as respondents. 2. **Stakeholder Objections:** ATL […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition for Truing up and determination of transmission tariff of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for DTL – EQ

Summary: —- ### Key Procedural Developments #### 1. **Compliance Status** – The counsel for DTL informed the Commission that the additional information requested by CERC in its previous order (RoP dated 20.11.2025) had been submitted via an affidavit dated January 8, 2026. – DTL also requested permission to file comprehensive **Written Submissions** to consolidate their […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition for Truing up and determination of transmission tariff of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for SPTL – EQ

Summary: —- ### Key Directives and Information Required from SPTL #### 1. **Compliance and Procedural Directives** – **Amended Petition:** SPTL must file an amended petition aligning with a consequential order dated 29.12.2025 in Petition No. 108/TT/2016, which itself was based on an APTEL judgment dated 25.3.2025. – **Notice to Respondents:** After filing the amended petition, […]

Draft KERC (Fee) (First Amendment) Regulation 2026 – EQ

Petition for extension of date of grid connectivity and commissioning of 7.8 MW Solar Plant for captive use due to occurnance of uncontrollable events – EQ

Summary: —- #### 1. Core Dispute: Extension Due to “Uncontrollable Events” – **The Petition:** Filed under **Section 86 (1) (c), (e), and (f)** of the Electricity Act, 2003, and Clause 3.9 of GERC Order No. 06 of 2024. – **Relief Sought:** Extension of the date for **grid connectivity and commissioning** for a 7.8 MW solar […]