Summary: —- **1. Issuing Authority:** Central Electricity Regulatory Commission (CERC), New Delhi. **2. Reference Details:** – **Petition Number:** 159/MP/2025 – **Subject:** Petition under Sections 63 and 79 of the Electricity Act, 2003 seeking relief under **Force Majeure (Article 11)** and **Change in Law (Article 12)** of the Transmission Service Agreement dated 11.11.2020. – **Project Context:** […]
Summary: — ## **1. Overview of the Proceedings** This document contains the **Record of Proceedings** from a hearing before the **Central Electricity Regulatory Commission (CERC)** in New Delhi. Two petitions are being considered, both filed by **Anantapur II Power Transmission Limited (AIIPTL)**, a wholly-owned subsidiary of Shivalaya Construction Ltd. — ## **2. Details of the […]
Summary: — ### **1. Regulatory Authority** * Central Electricity Regulatory Commission (CERC), New Delhi. * Proceedings conducted under the Electricity Act, 2003 and applicable CERC Tariff Regulations. ### **2. Petition Overview** * Filed by **Power Grid Corporation of India Limited (PGCIL)**. * Petition relates to determination of **transmission tariff for the 2024–29 tariff period**. * […]
Summary: — ### **1. Case Details** – **Petition No.**: 80/TT/2025 – **Subject**: Determination of **Transmission Tariff** for assets under the **Transmission System Strengthening Scheme for evacuation of power from Solar Energy Zones in Rajasthan (8.1 GW) under Phase-II-Part B1**. – **Petitioner**: **Power Grid Corporation of India Limited (PGCIL)** – **Respondents**: **Ajmer Vidyut Vitran Nigam Limited […]
Summary: —- **KEY PROCEEDINGS:** 1. **Name Change of Petitioner:** – Petitioner’s representative informed the Commission that the process of changing the company’s name is ongoing. – Requested permission to file an affidavit with supporting documents regarding the name change. 2. **Commission’s Direction:** – Petitioner permitted to file an affidavit within **one week**, placing on record […]
Summary: —- **Subject of Petition:** Power Grid Corporation of India Limited (PGCIL) has filed a petition for **determination of transmission tariff** from the Date of Commercial Operation (DOCO) until **31 March 2024** for specific transmission assets under a **renewable energy evacuation scheme** in Rajasthan. **Assets Involved:** – **Substation:** 400kV Bikaner-II Pooling Station (PS) – extension […]
Summary: — ### **Key Points:** 1. **Public Participation Invited:** – Interested persons may submit suggestions, comments, or objections in writing. – Must be sent to the **Secretary, MPERC** and copied to **MPPTCL**. – **Deadline:** Within **21 days** of publication of this notice (published on 28/11/2025). 2. **Access to Petition:** – Copy of the petition can […]