Summary: — ### Key Business and Regulatory Points #### 1. Core Objective and Legal Framework – **Purpose of the Petition:** The Petitioner sought the adoption of transmission charges for a new ISTS project by the Central Electricity Regulatory Commission (CERC) under **Section 63 of the Electricity Act, 2003**. – **Legal Basis (Section 63):** This section […]
Summary: — ### 1. Case Overview * **Petition No.:** 1029/TL/2025 * **Petitioner:** Navinal Transmission Limited (NNTL) * **Respondents:** Central Transmission Utility of India Limited (CTUIL) & Others. * **Subject:** Application for grant of a separate Transmission License for a transmission system at Navinal (Mundra) (GIS) under the **Regulated Tariff Mechanism (RTM) route**. * **Date of […]
Summary: — ### **1. Project Overview** * **Project Name:** Transmission system for proposed Green Hydrogen / Green Ammonia projects in Vizag area, Andhra Pradesh (Phase-I). * **Objective:** To create a transmission system capable of handling approximately 4,500-5,000 MW of power demand from new Green Hydrogen/Green Ammonia projects and datacenter loads in the Vizag region. * […]
Summary: — ### **SUBJECT OF PETITION** – Application under **Section 63 of the Electricity Act, 2003** for **adoption of transmission charges** discovered through competitive bidding for the **Inter-State Transmission System (ISTS)** for evacuation of power from **Kudankulam Unit 3 & 4 (2×1000 MW)** on a **Build, Own, Operate, Transfer (BOOT)** basis. — ### **KEY FINDINGS […]
Summary: — ### **Subject of the Petition** MITL filed under **Section 63 of the Electricity Act, 2003**, seeking: 1. **Adoption of transmission charges** discovered through a tariff-based competitive bidding process for a Green Hydrogen/Ammonia transmission project. 2. Inclusion of these charges in the **Point of Connection (POC) pool** under CERC regulations. 3. General prayers for […]
Summary: —- **1. Case Overview** – **Regulatory Body:** Central Electricity Regulatory Commission (CERC), New Delhi. – **Petitions:** Multiple petitions (572/TT/2025, 592/TT/2025, 575/TT/2025, 508/TT/2025, 511/TT/2025, 605/TT/2025, 579/TT/2025, 513/TT/2025, 514/TT/2025, 904/TT/2025). – **Subject:** Petitions for truing up of transmission tariff for the **2019–24 period** and determination of tariff for the **2024–29 period** for various transmission assets across […]
Summary: —- **1. Case Overview** – **Regulatory Body:** Central Electricity Regulatory Commission (CERC), New Delhi. – **Petition Number:** 375/TT/2025. – **Subject:** Petition for truing up of transmission tariff for the 2019–24 period and determination of tariff for the 2024–29 period for the 400 kV Transmission System associated with Farakka-I & II Super Thermal Power Stations […]
Summary: — **1. Overview of Petitions** All three petitions filed by **Power Grid Corporation of India Limited (PGCIL)** seek: – **Truing up** of transmission tariff for the period **2019–24**. – **Determination** of transmission tariff for the period **2024–29**. **2. Petition-wise Summary** | Petition No. | Scheme / Asset Description | Region | Key Respondents | […]
Summary: — ### **1. Nature of the Petition** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Respondents:** Tamil Nadu Power Distribution Corporation Limited (TNPDCL) and Others – **Subject:** Determination of **transmission tariff** for the **2024–29 tariff period** for the project: – **Establishment of 765/400/220 kV Substation at Kurnool-III** – **Extension of 765 kV […]