Summary: —- ### Key Procedural Developments #### 1. **Compliance Status** – The counsel for DTL informed the Commission that the additional information requested by CERC in its previous order (RoP dated 20.11.2025) had been submitted via an affidavit dated January 8, 2026. – DTL also requested permission to file comprehensive **Written Submissions** to consolidate their […]
Summary: —- ### Key Directives and Information Required from SPTL #### 1. **Compliance and Procedural Directives** – **Amended Petition:** SPTL must file an amended petition aligning with a consequential order dated 29.12.2025 in Petition No. 108/TT/2016, which itself was based on an APTEL judgment dated 25.3.2025. – **Notice to Respondents:** After filing the amended petition, […]
Summary: —- #### 1. Case Background and Legal Context – **Petitioner:** Power Transmission Corporation of Uttarakhand Limited (PTCUL), the state transmission utility. – **Respondents:** Power Grid Corporation of India Limited (PGCIL) and other stakeholders. – **Subject Asset:** The petition concerns the **400 kV Srinagar – Srinagar PH Transmission Line**, which is part of the “UITP […]
Summary: —- #### 1. The Dispute and Legal Context – **Petitioner:** NTPC Ltd., India’s largest energy conglomerate. – **Respondents:** A group of 26 electricity distribution companies, including APEPDCL (Andhra Pradesh), MPPMCL (Madhya Pradesh), NBPDCL & SBPDCL (Bihar), and MSEDCL (Maharashtra). – **Legal Basis:** The case is being heard under the CERC (Terms & Conditions of […]
Summary: — ### 1. Overview of the Hearing This document is a “Record of Proceedings” from a CERC hearing involving multiple tariff petitions filed by PGCIL. The primary purpose of these petitions is twofold: 1. **Truing-up (2019-24):** Adjusting the provisional tariff approved for the previous control period based on actual capital expenditure and performance. 2. […]
Summary: —- **1. Case Overview** – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Matters Heard:** Two separate petitions concerning transmission tariff determination for different regional systems. – **Petition No. 744/TT/2025:** Regarding assets under the “220 kV Srinagar-Leh Transmission System (SLTS)” in the Northern Region. – **Petition No. 529/TT/2025:** Regarding the “Chukha Transmission System” […]
Summary: —- #### Key Details: – **Petitioner:** Power Grid Corporation of India Limited (PGCIL). – **Regulatory Authority:** Central Electricity Regulatory Commission (CERC), New Delhi. – **Date of Order:** 26th February 2026. – **Project Name:** Transmission System for controlling high Short Circuit Current level at 400 kV Thiruvalam S/s (Southern Region). – **Asset Details:** – **Asset-1:** […]
Summary: — ### Detailed Analysis of the CERC Order #### 1. Background and Project Overview – **Petitioner:** Power Grid Corporation of India Limited (PGCIL), the Central Transmission Utility. – **Respondent:** Bangladesh Power Development Board (BPDB), the sole beneficiary of the transmission asset. – **Asset in Question:** 400kV D/C (02nd) Baharampur (POWERGRID) – Bheramara (BANGLADESH) transmission […]
Summary: —- **Objective:** This is a regulatory proceeding before the CERC where PTCUL is seeking approval for the transmission tariff of a specific 220 kV line. The tariff determines the revenue PTCUL can earn from this asset, which directly impacts its financial health and the transmission charges paid by its customers and other stakeholders. **Key […]
Summary: — #### Business & Regulatory Summary This document is a Record of Proceedings (RoP) from a regulatory hearing before the CERC. It outlines a tariff dispute and approval process for a major interstate transmission system asset. Key business and regulatory highlights include: – **Core Issue:** PGCIL, the central transmission utility, has filed a petition […]