### **1. Basic Project Information**
* **Project Title:** PV-System Goaltore Phase 2 (including Battery Energy Storage System – BESS)
* **Employer/Client:** West Bengal State Electricity Distribution Company Limited (WBSEDCL)
* **Financing Agency:** KfW Development Bank (German Financial Cooperation)
* **Procurement ID:** KfW 513025 / BMZ No. 202367985
* **Document Type:** Prequalification (PQ) Document for Consulting Services (Implementation Supervision Consultant)
* **Issue Date:** September 25, 2025
—
### **2. Project Background & Scope**
* **Objective:** To select a Consultant to supervise the implementation of a **100 MWAC solar PV power plant** with a **52 MWh Battery Energy Storage System** in Goaltore, West Bengal (Phase 2 of an existing project).
* **Project Model:** The main EPC (Engineering, Procurement, and Construction) contract will be awarded separately on a turnkey basis, including 5 years of O&M. This consultancy will oversee the EPC contractor.
* **Consultant’s Core Tasks (Scope of Services):**
1. **Design Review:** Review detailed engineering designs from the EPC contractor.
2. **Construction Supervision:** Supervise all works and installation of the PV plant and BESS until commissioning, following **FIDIC Yellow Book** (Design-Build) conditions.
3. **Contract & Claim Management:** Administer the EPC contract, handle claims, variations, and payments.
4. **Reporting & Disbursement Management:** Report to KfW and manage fund disbursements and cost control.
5. **ESHS Compliance Monitoring:** Supervise contractor compliance with Environmental, Social, Health, and Safety (ESHS) standards, aligned with **World Bank Environmental and Social Standards (ESS)** and national regulations.
—
### **3. Key Prequalification Requirements for Applicants**
* **Eligible Entities:** Private firms, government-owned entities (if commercially autonomous), or Joint Ventures (JVs).
* **Joint Venture (JV) Rules:**
* Maximum of **3 members** total (including Lead Consultant).
* All members are jointly and severally liable.
* An applicant (including affiliates/JV members) can only participate in **one application**.
* **Mandatory Financial Criteria:**
* **Average Annual Turnover (last 3 years):** ≥ EUR 600,000.
* For JVs: Combined total must meet requirement; **each member** must meet ≥50% of requirement; **Lead Consultant** must meet full requirement.
* **Current Ratio (average last 3 years):** ≥ 1.0.
* For JVs: **Lead Consultant** must meet this requirement.
* **Mandatory Management System Certifications (for Applicant or JV Lead):**
* Quality Management System: **ISO 9001** (or equivalent).
* Environmental Management System: **ISO 14001** (or equivalent).
* **Conflict of Interest:** Strict rules apply. Applicants must submit a declaration and will be disqualified for various conflicts, including having prepared project specifications, controlling/being controlled by other applicants, or having inappropriate relationships with WBSEDCL staff.
—
### **4. Application Process & Submission**
* **Platform:** Submission is **exclusively electronic** via the **Exfitender** e-procurement portal (`https://www.exfitender.de`). No physical submissions accepted.
* **Deadline:** **October 29, 2025, 12:00 Noon UTC (5:30 PM IST).**
* **Application Contents Must Include:**
1. Application Letter
2. Power of Attorney (if representative is not owner/director)
3. Company Presentation (max 10 pages)
4. **Mandatory Forms (Section III):**
* Form 1: Declaration of Undertaking (includes anti-corruption, eligibility declarations)
* Form 2: Declaration on Conflict of Interest
* Form 3: Declaration of Association (for JVs)
* Form 4: Financial Capacity Statement (with audited financials)
* Form 5: Project Experience References (max **10** references)
* Form 6: List of Available Expertise & Human Resource Capacity
* **Clarification Requests:** Must be submitted via Exfitender **14 days before** the application deadline.
—