Petition for determination of transmission tariff for Mysore Substation in Karnataka in the Southern Region β EQ
Summary:
β
###
**Case Summary**
* **Petition No.**: 275/TT/2025
* **Petitioner**: Power Grid Corporation of India Limited (PGCIL)
* **Respondents**: Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) and 14 others
* **Subject**:
Petition for **determination of transmission tariff** for the 2024β29 tariff period related to:
> β1X500 MVA, 400/220 kV ICT (4th) along with associated bays and equipment at Mysore Sub-stationβ
> under the project titled:
> βAugmentation of transformation capacity at Mysore Sub-station in Karnataka (Southern Region)β
* **Date of Hearing**: 22 July 2025
* **Coram**:
* Shri Jishnu Barua (Chairperson)
* Shri Ramesh Babu V.
* Shri Harish Dudani
* Shri Ravinder Singh Dhillon
β
###
**Proceedings and Submissions**
1. **PGCIL Submission**:
* PGCIL stated it had submitted additional details via **affidavit dated 13 June 2025** in response to the **technical validation letter**.
* The petitioner requested the Commission to **approve the tariff** for the stated asset.
2. **Commissionβs Direction to Respondents**:
* All Respondents were instructed to **file their replies within two weeks**.
* Replies should be shared with the Petitioner, who may file a **rejoinder within two weeks thereafter**.
β
###
**Key Directives from the Commission**
#### 1. **To the Petitioner (PGCIL)** β Submit the following within 2 weeks on affidavit:
a. **Detailed comparison** between **award cost and completion cost** of the project.
b. **Activity-wise delay justification** in the following prescribed format:
| Asset Activity-wise details | Original Schedule (Start-End) | Actual Schedule (Start-End) | Time Overrun (Days) | Reason for Delay |
| βββββββββ | ββββββββββ | βββββββββ | ββββββ- | βββββ- |
c. **Form 12** related to the transmission asset.
d. **Revised Cost Estimate-I** for the project.
#### 2. **To CTUIL (Central Transmission Utility of India Limited)** β Submit on affidavit within two weeks:
* Confirm whether the **timeline extension** under RTM (as per **MoM of 28th NCT meeting dated 21 March 2025**) has been implemented **for this specific asset**.
β
###
**Next Hearing**
* The case is scheduled for **next hearing on 16 September 2025**.