Petition for Truing up and the determination of transmission tariff for Line bays at Saharanpur (PG) in the Northern Region – EQ
Summary:
—
## **Case Summary – PGCIL (Saharanpur 220 kV Line Bays)**
**Forum:** Central Electricity Regulatory Commission (CERC), New Delhi
**Petition No.:** 192/TT/2025
**Date of Hearing:** 26 August 2025
**Coram:**
* Jishnu Barua, Chairperson
* Ramesh Babu V., Member
* Harish Dudani, Member
* Ravinder Singh Dhillon, Member
—
### **1. Case Background**
* **Petitioner:** Power Grid Corporation of India Limited (PGCIL).
* **Respondents:** Uttar Pradesh Power Corporation Ltd. (UPPTCL) & 15 others.
* **Subject:**
* Petition for **truing up of transmission tariff for 2019–24**, and
* **Determination of tariff for 2024–29**
* For transmission asset: **2 × 220 kV line bays at Saharanpur (PG)** under Northern Region scheme.
—
### **2. Proceedings**
* **UPPTCL Counsel (Sachin Dubey & team):** Filed reply on record.
* **PGCIL Representative:** Requested **one week’s time to file rejoinder** to UPPTCL’s reply; also asked for matter to be reserved for order.
—
### **3. Commission’s Directions**
* Allowed PGCIL to file rejoinder within **1 week**.
* **Order reserved**, subject to receipt of rejoinder.
—
### **4. Outcome**
* **Type of Order:** Procedural (Record of Proceedings).
* **Effect:** Case reserved for final order; pending rejoinder from PGCIL.
* **Status:** Awaiting Commission’s final tariff order.
—
For more information please see below link:
Related posts:
- Petition for Truing up and the determination of transmission tariff for transmission asset at Saharanpur (PG) in the Northern Region – EQ
- Petition for Truing Up and determination of transmission tariff for the “Combined Asset of Transmission System associated with Rampur HEP” in the Northern Region – EQ
- Petition for Truing up and determination of transmission tariff for utilized as Bus Reactor at Jaipur (South) Sub-station and Asset- II at Kota and Jaipur (South) under Transmission System in Northern Region – EQ
- Petition for Truing up and determination of Transmission Tariff with Northern Region Strengthening Scheme-XXII in Northern Region – EQ