**Subject:**
Determination of transmission tariff from the Commercial Operation Date (COD) to 31.3.2029 for assets: **02 Nos. 220 kV Line Bays** at the 400/220 kV Panchkula (Barwala) (PG) Sub-station, under the project “Implementation of 2 Nos. 220 kV line bays for interconnection with 220 kV Dera Bassi (PSTCL) Sub-station”.

**Petitioner:**
Power Grid Corporation of India Limited (PGCIL)

**Respondents:**
Punjab State Power Corporation Limited (PSTCL) and others

**Hearing Date:** 17.2.2026
**Next Hearing:** 16.4.2026

**Key Developments:**

1. **Petitioner’s Submission:**
– PGCIL requested that the transmission tariff be allowed as claimed.
– Filed Technical Validation letter and reply to the Record of Proceedings (RoP) dated 22.12.2025.
– No replies filed by any respondents so far.

2. **Commission’s Directions:**
– **PSTCL** directed to file an affidavit explaining reasons for **delay in commissioning the downstream asset** (within two weeks).
– All respondents given **two weeks** to file replies, with advance copy to PGCIL.
– PGCIL may file rejoinder within **two weeks** thereafter.

—-