1. Home
  2. Featured
  3. Office Memorandum – Force Majeure Clause (West Asia Situation) – EQ
Office Memorandum – Force Majeure Clause (West Asia Situation) – EQ

Office Memorandum – Force Majeure Clause (West Asia Situation) – EQ

0

Summary:

## Key Provisions & Business Implications

### 1. **West Asia Situation Deemed “War” – FM Trigger Confirmed**

| Aspect | Detail |
|——–|——–|
| **FM Definition** | Extraordinary events beyond human control – act of God, war, strike, riots, crimes |
| **Exclusions** | Negligence, wrongdoing, predictable/seasonal rain |
| **New Clarification** | “Ongoing West Asia situation should be treated as **war**” |

**Business Impact:**
Any government contractor (goods, consultancy, non-consultancy services, works) facing supply chain, logistics, labor, or other disruptions due to the West Asia crisis can now legitimately claim FM, provided the contract was **active and compliant** as of the cutoff date.

### 2. **Mandatory Contract Extension – 2 to 4 Months (No Penalty)**

| Condition | Requirement |
|———–|————-|
| **Eligible obligations** | Those due for completion on or after **February 28, 2026** |
| **Extension Period** | **Not less than 2 months, not more than 4 months** (decided case-by-case by procuring entity) |
| **Cost/Penalty** | **None** – no liquidated damages, penalties, or additional costs |

**Business Impact:**
Contractors need not negotiate extensions – the procuring entity **must** grant at least 2 months. For severe disruptions, up to 4 months can be requested. This provides **certainty** and protects against financial penalties.

### 3. **Eligibility Condition – “No Default” as of February 27, 2026**

| Scenario | FM Eligible? |
|———-|————–|
| Contractor was in **default** (delay, breach, non-compliance) as of **Feb 27, 2026** | **No** |
| Contractor was **compliant** as of Feb 27, 2026, but West Asia caused disruption thereafter | **Yes** |

**Business Impact:**
Contractors must be able to demonstrate **good standing** as of the day before the FM trigger. If already delayed before the crisis, FM cannot be invoked – even if the crisis worsens the situation.

### 4. **Limited Relief – Only Directly Attributable Non-Performance**

| Covered | Not Covered |
|———|————-|
| Non-performance **directly attributable** to West Asia disruptions | Non-performance unrelated to West Asia crisis |
| Suspension of obligations during FM period | Permanent excuse – obligations **revive** after FM ends |

**Business Impact:**
Contractors must establish a **clear causal link** between specific delays and the West Asia situation (e.g., blocked shipping routes, unavailability of imported components, labor shortages due to conflict). Vague claims will be rejected.

### 5. **Procedural Requirements – Timely Notice (≤14 Days)**

| Step | Requirement |
|——|————-|
| **Notice of FM** | Within **reasonable time as conditions permit** (guidance: **not later than 14 days** after occurrence) |
| **Retrospective claim** | **Not allowed** – cannot claim FM ex-post facto |
| **FM affecting procuring entity only** | Entity must similarly communicate to supplier |

**Business Impact:**
Contractors must **act quickly** – ideally within 14 days of the disruptive event. Delayed notice may invalidate the claim. Documentation of the disruption (e.g., shipping advisories, supplier communications, port closure notices) is essential.

### 6. **Termination Right if FM Exceeds 90 Days**

| Duration | Consequence |
|———-|————-|
| FM prevents performance for **>90 days** | Either party may **terminate the contract** |
| Financial repercussion | **None on either side** – no termination damages |

**Business Impact:**
If the West Asia crisis causes a continuous disruption beyond 90 days, both government and contractor have a **clean exit option** without liability. This protects both parties from indefinite suspension.

### 7. **Protection from Punitive Provisions**

| Without FM | With FM (Valid) |
|————|—————–|
| Delay/breach attracts sanctions, liquidated damages, blacklisting | **No sanctions** for delay/failure directly caused by FM event |

**Business Impact:**
Contractors are shielded from **financial penalties, performance bank guarantees invocation, and blacklisting** for the period of FM – but only for the specific obligations directly impacted.

## Comparison with Standard Force Majeure Clause

| Standard FM (as per Manuals) | This OM Clarification |
|——————————|———————-|
| War is a recognized FM event | West Asia situation **explicitly deemed war** |
| No fixed extension period | **Mandatory 2-4 months extension** |
| Termination after 90 days | Same – 90 days triggers termination option |
| Notice within reasonable time | Specific guidance: **≤14 days** |
| No explicit “no default” requirement | **Must not be in default as of Feb 27, 2026** |
| No distinction on direct vs. indirect impact | Only **directly attributable** non-performance covered |

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network