Petition for determination of the transmission tariff at Pune (Shikrapur) along with associated ICT and Line bays under “Western Region Expansion Scheme-XXVI” – EQ
Summary:
—
### **1. Key Hearing Details**
– **Date of Hearing:** 16.12.2025
– **Bench Members:**
– Shri Ramesh Babu V., Member
– Shri Harish Dudani, Member
– Shri Ravinder Singh Dhillon, Member
– **Parties Present:** Representatives from PGCIL, Central Transmission Utility of India Ltd. (CTUIL), and Maharashtra State Electricity Distribution Company Ltd. (MSEDCL).
—
### **2. Key Submissions & Requests**
– PGCIL representatives confirmed that all petitions are for **tariff determination for the 2024–29 period**.
– In Petition No. 831/TT/2025, PGCIL requested time to file the **CTUIL Completion Certificate**.
– **MSEDCL** (Respondent in Petition No. 826/TT/2025) sought **four weeks** to file its reply.
—
### **3. Commission’s Directions**
**(a) General Directions:**
– **Implead CTUIL** as a respondent in Petition No. 878/TT/2025 and serve a copy of the petition within one week.
– Issue notices to all respondents.
– Respondents to file replies within **four weeks**; PGCIL may file rejoinders within **two weeks** thereafter.
**(b) Specific Information Required from PGCIL (within four weeks):**
| **Petition No.** | **Required Information / Documents** |
|——————|———————————————————————————————————————————————————————————————————————————————————————|
| **826** | CTUIL Certificate (Regulation 27(1)(c) of Grid Code), Initial Spares details, Form 5A with award cost justification, Notional IDC computation in Excel, Form-9C in Excel, time overrun details with reasons. |
| **836** | Form 9C in Excel, Cash IDC Statement, reconciliation of Plant & Machinery cost for Initial Spares. |
| **742** | CMD Certificate (Regulation 26(3)(a) of Grid Code), RCE for cost overrun, Form-9C in Excel, clarification on Notional IDC claim, revised Notional IDC computation, detailed loan interest calculations, clarification on supply work dates. |
| **732** | Awarded vs. Completion Cost comparison, Notional IDC calculation in Excel, Form-9C in Excel, Cash IDC statement, Form 12 (time overrun), RCE-II for Asset-II. |
| **821** | Activity-wise time delay justification, shutdown-related delay details, RoW issue delay details, ACE details, Form-9C in Excel, interest rate calculations, P&M cost reconciliation, Notional IDC computation, revised Form-12. |
| **878** | Readiness status of downstream transmission system, P&M cost reconciliation, Form-9C in Excel, loan interest calculations, Initial Spares discharge statement, IDC discharge statement. |
| **831** | Completion Certificate from CTUIL, update on downstream asset completion by PSTCL, Notional IDC calculation in Excel. |
—