Petition for determination of transmission tariff for Providing Connectivity to M/s Greenko AP01 IREP Private Limited β EQ
Summary:
β
###
**Case Summary**
* **Petition No.**: 426/TT/2025
* **Petitioner**: Power Grid Corporation of India Limited (PGCIL)
* **Respondents**: Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) and 15 others
* **Subject**:
Determination of transmission tariff for the 2024β2029 tariff block for:
> βImplementation of 1 No. 400kV line bay at Kurnool New Sub-station to provide connectivity to M/s Greenko AP01 IREP Pvt. Ltd (2nd 400kV line bay for Greenko), Bay No.412.β
* **Date of Hearing**: 22 July 2025
* **Coram**: Shri Jishnu Barua (Chairperson), Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon
β
###
**Proceedings and Submissions**
1. **PGCILβs Submission**:
* The petition was filed to determine the transmission tariff for the above-stated asset.
* PGCIL submitted that they responded to a technical validation letter via an affidavit dated **13 June 2025**.
* They requested the Commission to approve the tariff as filed.
2. **Respondentβs Request** (TANGEDCO):
* Their legal counsel, Shri S. Vallinayagam, requested **additional time to file a reply**.
3. **Commissionβs Directions to Respondents**:
* All respondents were directed to **file their replies within two weeks**.
* Replies should be shared with the petitioner in advance.
* The petitioner may file a **rejoinder within two weeks thereafter**.
β
###
**Key Directives from the Commission**
#### 1. **To the Petitioner (PGCIL)** β Submit the following within 2 weeks on affidavit:
a. **Cost Comparison**: A detailed comparison between awarded cost and actual completion cost.
b. **Form 12 Submission**: Include activity-wise delay justification in the following format:
| Asset Activity-wise details | Original Schedule (Start-End) | Actual Schedule (Start-End) | Time Overrun (Days) | Reason for Delay |
| βββββββββ | ββββββββββ | βββββββββ | ββββββ- | βββββ- |
c. **Project Status**: Confirm whether **power flow has been achieved** in the stated asset.
#### 2. **To CTUIL (Central Transmission Utility of India Limited)** β Submit the following within 2 weeks on affidavit:
* Referencing the **28th NCT Meeting (MoM dated 21 March 2025)**, confirm whether the **timeline extension under RTM** (Real-Time Monitoring) was implemented for this specific transmission asset.
β
###
**Next Hearing**
* The Commission scheduled the **next hearing on 16 September 2025**.
β
For more information please see below link:


