Summary:

## 📌 Case Details

* **Authority:** Central Electricity Regulatory Commission (CERC), New Delhi
* **Petition No.:** 337/TT/2022
* **Petitioner:** Power Grid Corporation of India Limited (PGCIL)
* **Respondents:** Bihar State Power (Holding) Co. Ltd. (BSPHCL) & 16 others
* **Date of Hearing:** 16 September 2025
* **Coram:** Shri Jishnu Barua (Chairperson), Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon

## 📝 Subject

* Petition for **determination of transmission tariff (COD to 31.3.2024)** for one asset under **“Transmission System for Transfer of Power from generation projects in Sikkim to NR/WR (Part – B1)”** in the Eastern Region.

## ⚖️ Proceedings

* **PGCIL (Petitioner):** Reiterated submissions in the petition; sought permission to file written submissions.
* **Respondent (Sikkim Urja Ltd.):** Confirmed filing of reply on **2.9.2024**; PGCIL filed rejoinder on **27.9.2024**.
* **Other Respondents:** Advocates from BSPHCL and TUL also participated.
* **Commission’s Direction:** All parties to file **written submissions within 1 week**.

## 📅 Current Status

* **Order reserved** by CERC after hearing.