Petition for Truing up and determination of tariff for “System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)” – EQ
Petition for Truing up and determination of tariff for “System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)”
Summary:
—
### **Petition Overview**
* **Petitioner**: Power Grid Corporation of India Limited (PGCIL)
* **Respondents**: Uttar Pradesh Power Corporation Limited and 17 others
* **Subject**:
* **Truing up of tariff for the 2019–24 period**, and
* **Determination of tariff for the 2024–29 period**
for an asset under the project titled:
**“System Strengthening Scheme in South-Western Part of Northern Grid (Part-B)”**.
—
### **Hearing Details**
* **Date**: 22 July 2025
* **Coram**:
* Shri Jishnu Barua (Chairperson)
* Shri Ramesh Babu V. (Member)
* Shri Harish Dudani (Member)
* Shri Ravinder Singh Dhillon (Member)
* **Representatives Present**:
* For PGCIL: Shri Zafrul Hasan, Shri Vivek Kumar Singh, Shri Vishal Sagar, Ms. Supriya Singh, Shri Ranjeet Pandey, Shri Ashish Alankar
* For Respondents (BRPL & BYPL): Advocates Shri Adarsh Tripathi and Shri Ajitesh Garg
—
### **Proceedings Summary**
* PGCIL submitted that, following previous directives issued on **17 April 2025**, it had filed the **amended petition** via **affidavit dated 2 June 2025**, and requested the Commission to approve the tariff.
* The counsels for **BRPL and BYPL** requested additional time to file their replies.
—
### **Commission’s Directions**
#### **To Respondents (including BRPL & BYPL):**
* File their **replies within two weeks**, with advance copies served to PGCIL.
* PGCIL may file **rejoinders within two weeks** thereafter.
#### **To the Petitioner (PGCIL):**
Submit the following **on affidavit within two weeks**, with copies to the respondents:
1. **Clarify the basis** for the **treatment of unrecovered depreciation**.
2. **Justify the submission of fresh tariff forms** for **Additional Capital Expenditure (ACE)** incurred during 2019–24.
3. Resolve **discrepancy in capital cost claims**:
* In Petition No. **264/TT/2025**, PGCIL claimed **₹16,333.62 lakh** for reconductoring works.
* In compliance with Petition No. **94/TT/2024**, it claimed only **₹14,454.81 lakh** in the current petition.
* Provide explanation for the difference.
4. **Justify timing mismatch**:
* ACE has been claimed from **FY 2023–24**, but **de-capitalisation** from **FY 2024–25**.
* Explain the logic of ACE before asset was put to use.
5. Provide the **original date of de-capitalisation** of the asset.
—
### **Next Hearing**
* The petition is scheduled for **further hearing on 16 September 2025**.
—
For more information please see below link: