## **1. Nature of the Petition**
The petition has been filed by **Power Grid Corporation of India Limited (PGCIL)** seeking:
1. **Truing-up** of transmission tariff for the period **2019–24**.
2. **Determination of tariff** for the next control period **2024–29**.
The assets involved belong to the **“Common Transmission System for Phase-II Generation Projects in Odisha”**, which is part of the Eastern Region network.
The petition is filed under:
* **Section 62** and **Section 79(1)(d)** of the Electricity Act, 2003
* Relevant regulations under the **CERC Conduct of Business Regulations, 2023**
* **CERC Tariff Regulations, 2019 & 2024**
This shows the matter relates to **periodic tariff revision** of existing transmission assets.
—
## **2. Parties Involved**
### **Petitioner:**
**Power Grid Corporation of India Ltd. (PGCIL)**
### **Respondents:**
**Bihar State Power (Holding) Company Limited and others**
(indicating that multiple beneficiary utilities of the Eastern Region are respondents)
### **PGCIL Representatives Present:**
* Shri Ranjeet Pandey
* Shri Ashish Alankar
* Shri Amit Yadav
* Shri Arjun Malhotra
* Shri Vivek Singh
* Ms. Kirti
### **Hearing Bench:**
* **Shri Ramesh Babu V., Member**
* **Shri Harish Dudani, Member**
—
## **3. Proceedings and Submissions**
### **PGCIL’s Submission**
PGCIL informed the Commission that:
* They were **unable to submit the amended petition** as previously directed by CERC in the **RoP dated 26 August 2025**.
* They requested an **additional two weeks** to file the amended petition.
This indicates pending compliance with earlier regulatory directions.
—
## **4. Commission’s Directions**
After hearing the petitioner, the Commission issued the following instructions:
### **a) Filing of Amended Petition**
PGCIL must:
* File the **appropriately amended petition within two weeks**.
* Serve an **advance copy** to all respondents.
### **b) Notice to Respondents**
CERC directed that:
* **Notice be issued** to all respondents regarding the amended petition.
### **c) Timelines for Replies**
Respondents must:
* File their **replies within two weeks** of receiving the amended petition.
* Serve advance copies to PGCIL.
PGCIL may:
* File **rejoinders within one week** after receiving reply(s), if necessary.
These directions formally restart the review cycle for tariff determination.
—
## **5. Next Date of Hearing**
CERC scheduled the next hearing of the petition for:
### 👉 **15 January 2026**
The petition will be reviewed again after the parties complete their submissions.
—