Petition of the CERC (Conduct of Business) Regulations for NRSS XXIX Transmission Ltd – EQ

Summary: —- ### 1. Background: Factual & Procedural History **The Incident:** Tower no. 286 of the 400 kV Sambha–Amargarh line, located on a hill slope in the Rajouri region of Jammu & Kashmir, developed cracks in its revetment wall and structural distress. NRSS claimed this was due to **unauthorized excavation** by BRO for road expansion […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

In the matter of Approval of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) “Transmission System for connectivity of Essar Power Gujarat Limited” in the Western Region – EQ

Summary: — ## Key Correction Details | Asset | Original (Incorrect) Date | Corrected Date | |——-|————————–|—————-| | **Asset-1:** Extension of 400 kV Bachau Substation with line reactor + associated line bays | 9 August 2021 (unchanged) | 9 August 2021 (unchanged) | | **Asset-2:** Essar Gujarat TPS – Bachau 400 kV D/C (triple) line […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions for recognition and issuance of Renewable Energy Certificate for Renewable Energy Generation) Regulations for issuance of Renewable Energy Certificates – EQ

Summary: — ## ⚖️ Procedural History of the Petition | Date | Event | |——|——-| | 28.05.2021 | First hearing – Petition admitted; NLDC directed to file reply | | 21.06.2021 | NLDC filed reply | | 10.05.2023 | **Petition dismissed for non-prosecution** (Petitioner/counsel absent despite notice) | | 11.09.2023 | RPPL filed IA No. […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition of the Electricity Act (Promotion of Generation of Electricity from Must-Run Power Plant) of the CERC (Conduct of Business) Regulations for solar PV power project with BESS at South Andaman – EQ

Summary: — ## 📄 Case Overview | Parameter | Details | |———–|———| | **Petition No.** | 171/MP/2024 | | **Petitioner** | NLC India Limited (NLCIL) | | **Respondent** | Electricity Department, Andaman | | **Subject** | Compensation for breach of **Must-Run status** of solar PV + BESS project | | **Date of Hearing** | 25 […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition of the CERC (Connectivity and General Network Access to the lnter-State Transmission System) and (Conduct of Business) Regulations at Solapur – EQ

Summary: — ## 📄 Case Overview | Parameter | Details | |———–|———| | **Petition No.** | 149/MP/2026 along with IA No. 45/2026 | | **Petitioner** | ReNew Green Energy Solutions Private Limited (RGESPL) | | **Respondent** | Central Transmission Utility of India Limited (CTUIL) | | **Subject** | Relief against CTUIL regarding grant of connectivity […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition of the CERC (Deviation Settlement Mechanism and Related Matters) (“2024 DSM Regulations”) and (Conduct of Business) Regulations – EQ

Summary: — ### Business Points 1. **Pending Regulatory Risk for Vena Energy (VEVPL):** The matter is now reserved for order. VEVPL faces an uncertain financial or operational outcome depending on the Commission’s ruling under the 2024 DSM Regulations. Management should assess potential liabilities or claims related to deviation settlement. 2. **Time-Sensitive Compliance:** VEVPL has been […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

In the matter of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Truing up and determination of the transmission tariff under “System Strengthening-XXIV” in the Southern Region – EQ

Summary: — ## **1. Assets Covered (Combined Asset)** | Asset | Description | COD | Time Overrun (condoned) | | :— | :— | :— | :— | | **Asset-A** | LILO of Kurnool–Thiruvalam 765kV D/C line + 765/400kV GIS substation at Cuddapah (2×1500 MVA ICT + 2×240 MVAR bus reactors) | 25.10.2018 | 106 […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition for truing up and determination of transmission tariff for the Kaiga Project in the Southern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Summary: — ## Key Directions Issued by CERC ### For Petition No. 412/TT/2025: 1. **Item-wise details** of Additional Capital Expenditure (ACE) claimed for 2019-24 and projected for 2024-29 – due to significant difference between approved and claimed figures. 2. **Equipment-wise cost estimate** for ACE projected for 2024-29. 3. **Justification & supporting documents** for contingency liability […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition for Approval of tariff with other States in the CERC (Sharing of Inter-State Transmission Charges and Losses) (Terms and Conditions of Tariff) and (Conduct of Business) Regulations – EQ

Summary: — ### **Subject of Tariff Approval** Five **natural inter-State transmission lines** owned by PTCUL that are incidental to inter-State transmission. Tariff approval is required for: – Operation & Maintenance (O&M) expenses – Inclusion in POC charges (so that users across states share the cost) ### **Hearing Details** – **Date of Hearing:** 19 March 2026 […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Truing up and determination of the transmission tariff for MSETCL owned Transmission Lines/Systems to other States – EQ

Summary: — ## **1. Case Overview** | **Parameter** | **Details** | | — | — | | **Petitioner** | Maharashtra State Electricity Transmission Company Limited (MSETCL) | | **Respondents** | Power Grid Corporation of India Limited (PGCIL) and others (including KPTCL) | | **Subject** | Truing up of transmission tariff for **2019–24 period** (under Tariff […]

Petition of the Power Purchase Agreement executed between Eden Renewable Alma Private Ltd. and Solar Energy Corporation of India Ltd. for Change in Law events – EQ