1. Home
  2. Policy & Regulation
  3. Petition for Truing up and determination of transmission tariff for Bawana – Mandaula Double Ckt. and Bamnauli – Ballabhgarh Double Ckt. transmission lines as CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ
Petition for Truing up and determination of transmission tariff for Bawana – Mandaula Double Ckt. and Bamnauli – Ballabhgarh Double Ckt. transmission lines as CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Petition for Truing up and determination of transmission tariff for Bawana – Mandaula Double Ckt. and Bamnauli – Ballabhgarh Double Ckt. transmission lines as CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

0
0

Summary:

### **1. Overview & Context**
* **Document Type:** CERC Order/Proceeding from a hearing held on **13 January 2026**.
* **Core Subject:** Hearing for two interconnected tariff petitions filed by **Delhi Transco Limited (DTL)**, concerning the same set of critical 400 kV transmission lines in the Delhi region.
* **Legal Framework:** Petitions filed under **Section 62** of the Electricity Act, 2003, and relevant CERC Tariff Regulations for different control periods.
* **Key Participants:** DTL (Petitioner), Power Grid Corporation of India Ltd (PGCIL), BSES Rajdhani Power Ltd (BRPL), and BSES Yamuna Power Ltd (BYPL).
* **Next Hearing Date:** **17 February 2026**.

### **2. Key Proceedings & Directives from the Hearing**
1. **DTL’s (Petitioner) Submission:**
* Requested **2 days** to submit additional information sought by the Commission in a previous hearing (20 Nov 2025) **in a sealed cover**.
2. **Respondents’ Requests:**
* **BYPL & BRPL (Petition 343):** Counsel for the Delhi distribution companies (BRPL & BYPL) sought **2 weeks** to file a reply to any additional information DTL submits.
* **BRPL (Petition 175):** Sought time to file its reply to the older, remanded petition.
3. **Commission’s Directives:**
* **To All Respondents (PGCIL, BRPL, BYPL):** File their respective replies to the petitions **within two weeks**, with a copy to DTL.
* **To DTL (Petitioner):** May file a rejoinder (rebuttal) to the replies **within one week** of receiving them.
* **Adjournment:** Matters adjourned to **17 February 2026** for the next hearing.

### **3. Business & Regulatory Implications**
* **Financial Impact for Delhi:** The outcome will determine the finalized transmission costs that DTL (and ultimately Delhi consumers via BRPL/BYPL) must pay for using these critical inter-state lines, impacting power purchase costs.
* **Revenue Certainty for PGCIL:** The truing up for 2019-24 will settle any pending revenue adjustments with PGCIL as the line owner.
* **Clearing Regulatory Backlog:** The hearing on the **remanded petition (175/2017)** is crucial to close a long-pending regulatory issue from the previous tariff period.
* **Confidentiality of Data:** DTL’s submission in a **”sealed cover”** suggests the information may be commercially sensitive or pertain to contested capital costs, to be reviewed first by the Commission.
* **Stakeholder Alignment:** The active participation of Delhi’s discoms (BRPL/BYPL) highlights their direct financial interest as the ultimate payers of the determined transmission charges.

### **4. Next Steps & Critical Path**
* **Immediate (2 days):** DTL to submit sealed-cover information.
* **Within 2 Weeks:** All respondents (PGCIL, BRPL, BYPL) to file their replies.
* **Within 3 Weeks:** DTL to file rejoinders, if needed.
* **Next Hearing:** **17 February 2026** – Likely for arguments based on the newly submitted information, replies, and rejoinders.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network