Petition for Truing up and determination of Transmission Tariff for North Eastern Region of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Petition for Truing up and determination of Transmission Tariff for North Eastern Region of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

0
0

Summary:

### Key Points:

#### Petitions Overview:
All petitions are filed by **PGCIL** under **Section 62 read with Section 79(1)(d)** of the Electricity Act, 2003, and relevant **CERC Tariff Regulations (2019 and 2024)** and **Conduct of Business Regulations (2023)**. The petitions seek:

1. **Truing up of transmission tariff** for the period **2019–24** (adjusting past revenues/costs to reflect actuals).
2. **Determination of transmission tariff** for the next tariff block **2024–29**.

The specific petitions are:

1. **Petition No. 15/TT/2025**: For assets under **”NERSS-II-B”** (North Eastern Region Strengthening Scheme-II, Part-B).
2. **Petition No. 22/TT/2025**: For assets under **”ERSS-X”** (Eastern Region Strengthening Scheme-X).
3. **Petition No. 58/TT/2025**: For assets under **”Transfer of Power from Generation Projects in Sikkim to NR/WR Part-A”**.
4. **Petition No. 60/TT/2025**: For assets under **”Transmission system associated with Darlipalli TPS”**.
5. **Petition No. 93/TT/2025**: For assets under **”ERSS-XIII”** (Eastern Region Strengthening Scheme-XIII).

#### Proceedings:
* **No respondents** were present at the hearing despite notice.
* The Commission **re-issued notices** to all respondents and granted them **two weeks** to file replies.
* PGCIL may file a rejoinder within **one week** after receiving replies.
* Specifically for **Petition No. 58/TT/2025**, the Commission directed PGCIL to **justify a claim of ₹83.04 Lakh** for Additional Capital Expenditure (ACE) beyond the cut-off date under Regulation 24(1)(a) of the 2019 Tariff Regulations.

#### Next Hearing:
All matters are listed for further hearing on **September 30, 2025**.

—-