1. Home
  2. Policy & Regulation
  3. Petition for truing up and determination of transmission tariff for the Kaiga Project in the Southern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ
Petition for truing up and determination of transmission tariff for the Kaiga Project in the Southern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Petition for truing up and determination of transmission tariff for the Kaiga Project in the Southern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

0
0

Summary:

## Key Directions Issued by CERC

### For Petition No. 412/TT/2025:
1. **Item-wise details** of Additional Capital Expenditure (ACE) claimed for 2019-24 and projected for 2024-29 – due to significant difference between approved and claimed figures.
2. **Equipment-wise cost estimate** for ACE projected for 2024-29.
3. **Justification & supporting documents** for contingency liability claim of **₹8,752.92 lakh (₹875.29 crore)** .

### For Petition No. 578/TT/2025:
– **Equipment-wise cost estimates** for ACE claimed (2019-24) and projected (2024-29).

### For Petition No. 599/TT/2025:
– **Interest During Construction (IDC) sheets** in Excel format for all assets.

### General Directions:
– POWERGRID to submit information **on affidavit** within **two weeks** (by ~2 April 2026) with advance copy to Respondents.
– **Respondents** (State DISCOMs & others) to file replies within **one week** thereafter.
– **POWERGRID** may file rejoinder within **one week** after replies.
– **Orders reserved** by CERC subject to above compliance.

# Business Points & Implications

| Business Aspect | Implication |
|—————-|————–|
| **Regulatory Scrutiny on Capex** | CERC is closely examining POWERGRID’s ACE claims due to large deviations from approved figures. Transmission licensees must maintain rigorous cost tracking and justification. |
| **Contingency Liability Risk** | The ₹875.29 crore contingency claim is under scrutiny. If disallowed, POWERGRID’s regulated equity and return on equity (RoE) will reduce, impacting profitability. |
| **IDC Transparency Required** | Excel-based IDC sheets for all assets (Petition 599) signal CERC’s demand for granular, auditable data. Other utilities should expect similar formatting requirements. |
| **Tariff Certainty Delayed** | Final tariff orders for 2024-29 period will be deferred until compliance submissions and replies are completed. DISCOMs face continued tariff uncertainty. |
| **DISCOM Opportunity** | Respondents (state DISCOMs like TANGEDCO, MPPower) can challenge inflated ACE/IDC claims to reduce their transmission charges payable to POWERGRID. |
| **Precedent for Future Petitions** | CERC’s directions set a benchmark: ACE claims must be justified equipment-wise, and contingency liabilities need strong documentary support. |
| **Nuclear Evacuation Infrastructure** | Kaiga 3 & 4 are nuclear assets. Timely tariff finalization ensures stable revenue for evacuation infrastructure, impacting nuclear power dispatch in Southern Region. |
| **Compliance Deadline Pressure** | POWERGRID has only 2 weeks to compile detailed equipment-wise ACE data – may require internal resource reallocation. |
| **Virtual Hearing Efficiency** | CERC continues to use virtual hearings, reducing legal travel costs for utilities and DISCOMs. |

## Stakeholder-Specific Takeaways

| Stakeholder | Action / Implication |
|————-|———————-|
| **POWERGRID** | Submit robust, equipment-wise ACE justification with IDC sheets in Excel; contingency liability needs third-party validation. |
| **State DISCOMs (Tamil Nadu, MP, others)** | File timely replies challenging any inflated ACE/IDC; engage tariff consultants if needed. |
| **Other Transmission Licensees** | Anticipate similar detailed ACE/IDC scrutiny in their own tariff petitions; prepare equipment-wise cost data upfront. |
| **Nuclear Power Operator (NPCIL)** | Tariff finalization for evacuation lines affects project viability for future nuclear plants. |
| **Investors in POWERGRID Bonds/Equity** | Monitor outcome – disallowance of ACE or contingency claims could impact regulated RoE (~15.5%) and cash flows. |

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network