### **Case Information**

– **Petition No.**: 412/TT/2025
– **Subject**: Petition for truing up of transmission tariff for the **2019–24 period** and determination of transmission tariff for the **2024–29 period** for the Combined Transmission System associated with the **Kaiga 3 & 4 (2×235 MW) Project** in the Southern Region.
– **Petitioner**: Power Grid Corporation of India Limited
– **Respondents**: Tamil Nadu Generation and Distribution Corporation Limited & Others
– **Date of Hearing**: December 11, 2025
– **Coram**: Shri Ramesh Babu V., Member
Shri Harish Dudani, Member

### **Key Proceedings**

1. **Petitioner’s Submission**: The petition seeks truing up of transmission tariff for the period **2019–24** and determination of tariff for **2024–29**.
2. **Petitioner’s Request**: Six weeks’ time was sought to file the **Revised Cost Estimates (RCE-III)** in this matter.
3. **Commission’s Direction**: The Commission granted **six weeks** to submit the RCE-III.
4. **Directions to Respondents**: Respondents must file their replies, if any, within **two weeks** on affidavit, with an advance copy to the petitioner. The petitioner may file a rejoinder within **two weeks** thereafter.
5. **Next Hearing**: Listed for hearing on **March 19, 2026, at 2:30 PM**.

### **Document Authentication**

– **Signed by**: T. D. Pant, Joint Chief (Law)