1. Home
  2. Policy & Regulation
  3. Petition of the CERC (Conduct of Business), (Indian Electricity Grid Code) and (Terms and Condition of Tariff Regulations) for the Transmission System of Kallam Transmission Limited in the Western Region – EQ
Petition of the CERC (Conduct of Business), (Indian Electricity Grid Code) and (Terms and Condition of Tariff Regulations) for the Transmission System of Kallam Transmission Limited in the Western Region – EQ

Petition of the CERC (Conduct of Business), (Indian Electricity Grid Code) and (Terms and Condition of Tariff Regulations) for the Transmission System of Kallam Transmission Limited in the Western Region – EQ

0
0

Summary:

—-

**1. Document Nature & Core Issue:**
* This is a **regulatory proceeding record** from the **Central Electricity Regulatory Commission (CERC)**.
* **Petition No.:** 844/TT/2025.
* **Core Business Issue:** Determination of the **transmission tariff** for a specific electricity transmission asset under the **Regulated Tariff Mechanism (RTM)**.
* **Petitioner:** Kallam Transmission Limited (KTL).
* **Asset:** 1 No. 400 kV bay at Kallam PS, built to interconnect a renewable energy (RE) project by Torrent Solar Power Private Limited.
* **Tariff Period Sought:** From the Commercial Operation Date (COD) to **31st March 2029**.

**2. Current Status & Commission’s Directive:**
* A hearing was held on **20th January 2026**.
* The Commission has **not granted the requested tariff approval**.
* Instead, it has issued a detailed directive requiring KTL to provide significant clarifications and additional documentation **within two weeks**.
* The next hearing is scheduled for **19th March 2026**.

**3. Key Information Requests & Concerns Raised by CERC:**
The Commission’s queries indicate **critical scrutiny of KTL’s financial and project execution claims**. The required information falls into several high-risk areas for tariff determination:

* **A. Financial Consistency & Validation:**
1. **Capital Cost Mismatch:** Clarify discrepancies between the capital cost stated in the petition and the Auditor’s Certificate.
2. **Equity Contribution Mismatch:** Clarify discrepancies in equity contribution figures between the petition and Tariff Form-8.
3. **Tax Rate Justification:** Provide supporting documents for the tax rate used to “gross up” the Return on Equity (ROE)—a direct input affecting the final tariff.
4. **Financing Structure:** Explain the rationale for taking a loan from the parent company (an Infrastructure Investment Trust) instead of traditional banks/financial institutions. This likely relates to scrutiny of interest rates and arm’s-length transactions.

* **B. Operational & Planning Scrutiny:**
5. **Legible Tariff Forms:** Submit clear copies of key statutory forms (Tariff Forms 2 & 5), indicating initial submissions were inadequate.
6. **Liability Flow for ACE:** Submit a Liability Flow Statement for the Additional Capital Expenditure (ACE) planned for 2024-29, ensuring expenditure phasing is justified.
7. **ACE Justification:** Provide a detailed, asset-wise/work-wise breakdown of:
* Original project scope and cost estimates.
* Liabilities payable in the future.
* Works deferred from the original scope.
* This is to rigorously justify the need for the proposed Additional Capital Expenditure (ACE).

* **C. Security Assessment:**
8. **Security Requirements:** Detail the assessment for security requirements (like Letter of Credit, Bank Guarantee) for the upcoming tariff period, linking financial security to project risk.

**4. Implications for Business & Stakeholders:**

* **For Kallam Transmission Ltd (KTL):**
* **Approval Delay & Revenue Risk:** The tariff start date is delayed until these clarifications are satisfactorily addressed, directly impacting revenue certainty.
* **Regulatory Scrutiny:** The Commission is deeply examining cost prudency, financing choices, and future expenditure plans. Inadequate responses could lead to disallowance of costs, reducing the allowable tariff.
* **Action Required:** KTL must urgently compile a comprehensive, audit-backed response to all eight points. The quality of this submission will be critical for securing favorable tariff terms.

* **For Torrent Solar Power Pvt Ltd (Off-taker/RE Generator):**
* The tariff determined for this transmission bay will become a **pass-through cost** affecting the overall cost of power evacuation from their solar project.
* Delays or higher-than-expected tariffs determined by CERC could impact their project economics.

* **For Investors/Lenders (including the InvIT Parent):**
* The Commission’s questions about intra-group lending and capital cost validation highlight **governance and financial structuring risks**.
* The final tariff order will impact the project’s debt service coverage ratio and equity returns.

* **For the Market (Other Transmission Developers):**
* This proceeding sets a precedent for CERC’s scrutiny of **InvIT-backed transmission projects** and its approach to **Additional Capital Expenditure (ACE)** claims in the current regulatory cycle.

—-

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network