Summary:

β€”

### πŸ“„ **Gujarat Electricity Regulatory Commission (GERC)**

**Daily Order in Petition No. 2514 of 2025**
**Date of Order:** 04 August 2025
**Petitioner:** German TMX Pvt. Ltd.
**Respondent:** Gujarat Energy Transmission Corporation Ltd. (GETCO)
**Bench:** S.R. Pandey and Mehul M. Gandhi

β€”

### πŸ” **Case Background:**

German TMX Pvt. Ltd. filed a petition under Sections **86(1)(c), (e), and (f)** of the Electricity Act, 2003 and relevant **GERC regulations (80 & 82)**. The company sought:

* **Extension of time** for the **Scheduled Commercial Operation Date (SCOD)** of its hybrid renewable energy project.
* Relief under **unforeseen and uncontrollable events**.
* Interim protection to avoid any coercive action by GETCO, the transmission utility.

β€”

### πŸ“‘ **Status of the Petition:**

* **IA No. 58/2025:** Urgent listing application.
* **IA No. 59/2025:** Request for **interim stay/injunction** and status quo on connectivity.

β€”

### βš™οΈ **Project Details by Petitioner:**

* Installed Capacity:

* **6.3 MW Wind**
* **5.5 MW Solar**
* **Total Commissioned Capacity: 11.8 MW** out of the planned **14.5 MW Hybrid Power Project**
* Balance capacity and evacuation systems are under development.

β€”

### βš–οΈ **Hearing Highlights (29 July 2025):**

* GETCO’s Advocate (**Utkarsh Singh**) requested **adjournment** to file a reply, having just received the petition.
* Petitioner’s counsel (**Purusharth Singh** and team) did **not object** to the adjournment but requested **status quo** on connectivity and assurance against coercive steps (like forfeiture of Bank Guarantee).
* Petitioner also committed to **extend the Bank Guarantee**.

β€”

### 🧾 **Commission’s Orders:**

1. **GETCO to file its reply within two weeks**, and Petitioner to file a **rejoinder within one week thereafter**.
2. **IA No. 58 of 2025** (for urgent listing) disposed of since the matter was heard on the listed date.
3. Parties directed to **complete pleadings** before the next hearing.
4. **Next hearing date will be notified separately**.

β€”

### πŸ›οΈ **Outcome:**

The Commission accepted the request for time extension in filing and ensured that procedural fairness is maintained. Meanwhile, connectivity and project status remain protected under status quo conditions.

β€”

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network