Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations with respect to Transmission License to SR WR Power Transmission Ltd – EQ
Summary:
—
### Nature of Filing
Regulatory Petition | Transmission License & Tariff Adoption
Filed under Electricity Act, 2003
### Petition Details
**Petition No. 885/TL/2025**
Application under Sections 14 & 15 of the Electricity Act, 2003 for grant of Transmission License
**Petition No. 884/AT/2025**
Application under Section 63 of the Electricity Act, 2003 for adoption of transmission charges discovered through Tariff-Based Competitive Bidding (TBCB)
### Project Description
Grant of transmission license and adoption of tariff for the project titled:
**“Inter-Regional Strengthening between Southern Region (SR) Grid and Western Region (WR) Grid”**
The transmission system is being established under the TBCB framework.
### Petitioner
SR WR Power Transmission Limited (SWPTL)
A 100% wholly owned subsidiary of Power Grid Corporation of India Limited (PGCIL)
### Respondents
Central Transmission Utility of India Limited (CTUIL) & Others
### Date & Venue of Hearing
* **Date of Hearing:** 23 December 2025
* **Next Hearing Date:** 13 January 2026
* **Venue:** CERC, New Delhi
### Commission Bench (Coram)
* Shri Jishnu Barua – Chairperson
* Shri Ramesh Babu V. – Member
* Shri Harish Dudani – Member
* Shri Ravinder Singh Dhillon – Member
### Key Submissions
* The petitioner submitted that both petitions have been filed for:
* Grant of transmission license
* Adoption of transmission charges discovered through TBCB
* Compliance with all applicable Transmission License Regulations has been confirmed by the petitioner
### Directions Issued by the Commission
* Petitions admitted by the Commission
* Notices issued to all respondents
* Respondents directed to file replies within **two weeks**
* Petitioner allowed to file rejoinders within **one week** thereafter
—-
For more information please see below link: