Summary: — ### **1. Overview** This is a **Record of Proceedings** from the **Central Electricity Regulatory Commission (CERC)**, New Delhi, regarding **Petition No. 92/TD/2026**. – **Petitioner:** EKI Energy Services Limited (EESL) – **Date of Hearing:** 7th April 2026 – **Purpose:** Application under **Section 14** and **Section 15(1)** of the Electricity Act, 2003, read with **Regulation […]
Summary: — ## 📋 Two Petitions Filed ### Petition No. 133/TL/2026 | Field | Details | |——-|———| | **Subject** | Application under Sections 14 & 15 of the Electricity Act, 2003 read with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations, 2024 | | **Purpose** | Seeking **grant […]
Summary: —- ### Background Statement: – Under GNA Regulations, Connectivity Applicants must achieve three key milestones: 1. **Submission of land documents** (50% of required land) 2. **Achieving Financial Closure (FC)** 3. **Achieving Commercial Operation Date (COD)** – Failure to meet timelines results in **revocation of Connectivity** and encashment of Bank Guarantees. – Many entities have […]
Summary: — 1. **Implead additional Respondents** – The Petitioner shall implead: – All beneficiaries of the **Western Region**, – **M/s Apraava Energy Pvt. Ltd.**, – **MPPTCL** (Madhya Pradesh Power Transmission Company Limited). File an amended memo of parties within **three days**. 2. **Admission & Notice** – The petitions are **admitted**. Notice shall be issued to […]
Summary: — ### **Project Specifics** – **Location:** Navinal (Mundra), Gujarat – **Purpose:** Transmission system for providing **connectivity to Renewable Energy (RE) applicants** at Navinal (Mundra) GIS (Gas Insulated Substation) – **Route:** **Regulated Tariff Mechanism (RTM)** – meaning the transmission asset will earn a regulated return on equity and cost-plus tariff, as opposed to competitive bidding […]
Summary: — **Case Background:** The petitioner, **NERGS-I Power Transmission Limited (NREGSPTL)** , filed a petition seeking a transmission license from the Central Electricity Regulatory Commission (CERC). The license was required to develop and operate an Inter-State Transmission System (ISTS) under the “North Eastern Region Generation Scheme-I (NERGS-I)” project. **Key Development & Petitioner’s Position:** During the […]