Petition with the CERC (Procedure, Terms and Conditions for Grant of Transmission Licence and other related matters) Regulations to Navinal Transmission Limited – EQ
Summary:
—-
## **1. Background and Objective of the Petition**
Navinal Transmission Limited (NTL) filed a petition before the Central Electricity Regulatory Commission (CERC) seeking a transmission licence under Sections 14, 15 and 79(1)(e) of the Electricity Act, 2003.
The objective: **to establish an Inter-State Transmission System (ISTS)** for the **Network Expansion Scheme in Navinal (Mundra), Gujarat** required for drawal of power for bulk consumers, distribution licensees, and potential green hydrogen/ammonia facilities.
The scheme will be developed on a **BOOT (Build-Own-Operate-Transfer)** basis.
—
## **2. Scope of the Transmission Project**
The project includes major infrastructure components such as:
* Establishment of a **765/400 kV GIS substation** at Navinal with **4×1500 MVA ICTs**, bus reactors, line bays, and provisions for future expansion.
* **LILO of Bhuj-II – Lakadia 765 kV D/C line** at Navinal.
* Installation of **switchable line reactors**.
* Associated GIS diameter completions and multiple provisions for future load, including green hydrogen/ammonia integration.
Scheduled COD: **21 months from effective date (14 July 2026)**.
—
## **3. Selection of Developer Through Tariff-Based Bidding**
PFC Consulting Ltd. (PFCCL), as Bid Process Coordinator, ran the competitive bidding.
**Adani Energy Solutions Limited (AESL)** emerged as the **winning bidder**, quoting annual transmission charges of **₹2987.14 million/yr**, and thus took over the SPV (NTL).
—
## **4. Public Notice and Initial Procedural Compliance**
CERC issued a public notice inviting objections; **no objections were received**.
The Commission then examined the project readiness, technical requirements, and compliance with applicable regulations, including **2024 Transmission Licence Regulations**.
—
## **5. Key Issue: Responsibility for Cost of Augmentation Under Regulation 12.5**
A central question that arose:
### **Who should bear the cost of necessary ISTS augmentation (ICTs, bays, connectivity infrastructure)?**
CTUIL submitted that, as per **Regulation 12.5**, bulk consumers and distribution licensees seeking direct ISTS connection must pay for:
* The dedicated line to ISTS, AND
* Necessary augmentation (e.g., ICTs & associated bays) required to integrate them.
Entities involved included:
* **MPSEZ Utilities Ltd. (MUL)** – distribution licensee
* **Kutch Copper Ltd. (KCL)** – bulk consumer
* **Mundra Petrochem Ltd. (MPL)** – bulk consumer
These entities had significant GNA/GNARE allocations but argued that they should not be required to submit **Conn-BG2** or bear augmentation costs.
—
## **6. Arguments by Bulk Consumers (KCL & MPL)**
KCL and MPL strongly opposed CTUIL’s demand for a **Conn-BG2**, arguing:
* GNA Regulations do **not** mandate Conn-BG2 for bulk consumers.
* Imposing Conn-BG2 would **blur distinction** between “connectivity” (for generators) and “GNA” (for bulk consumers).
* Would lead to **discrimination** against bulk consumers applying directly vs. through STU.
* They have already invested **thousands of crores**, so concerns of “non-serious” applicants are baseless.
* Any such requirement would require a **formal amendment** to GNA Regulations — not a judicial order.
—
## **7. CTUIL’s Rebuttal and Planning History**
CTUIL clarified that:
* The scheme was **originally** planned **solely for bulk consumer load** (4000 MW).
* Later, MNRE shared potential green hydrogen/ammonia demand, **not actual applicants**, causing the project to evolve into an ISTS common scheme.
* However, **Regulation 12.5 still applies**—bulk consumers must bear augmentation costs.
* To prevent stranded ISTS investment if bulk consumers withdraw GNA later, **security mechanism (BG)** is necessary.
—
## **8. CERC’s Analysis and Findings**
CERC conducted a detailed review of:
* GNA Regulations
* Multiple CMETS-WR and NCT meeting deliberations
* Historical planning documents
* Legal interpretations raised by parties
CERC’s conclusions:
### **A. Regulation 12.5 is unambiguous**
Bulk consumers & distribution licensees seeking direct ISTS connectivity **must bear the cost of necessary augmentation**.
### **B. Immediate Augmentation Costs Must Be Paid**
ICTs and associated bays at the ISTS substation constitute necessary augmentation and must be paid for by the beneficiaries proportional to their GNA/GNARE.
### **C. To safeguard ISTS investments:**
Bulk consumers must deposit the proportional cost of ICTs and bays.
If they fail to pay within 30 days, **their GNA/GNARE will be cancelled**.
### **D. CTUIL must calculate exact cost per entity**, based on up-to-date cost data or NCT guidance.
### **E. No merit in claims of discrimination or improper regulatory interpretation** by KCL/MPL.
—
## **9. Final Order of the Commission**
CERC **grants** the transmission licence to **Navinal Transmission Limited**, subject to key conditions:
### **Mandatory Cost Contribution by GNA/GNARE Grantees**
* Bulk consumers & discoms must deposit ICT-related augmentation costs in proportion to their GNA.
* CTUIL will notify exact payable amounts.
* Non-payment = GNA cancellation + BG actions per GNA Regulations.
### **Financial and Operational Conditions**
* Licence valid for **25 years**.
* Must comply with:
* 2024 Transmission Licence Regulations
* CERC Grid Code
* Performance Standards
* CEA technical standards
* Must provide **non-discriminatory open access**.
* No electricity trading allowed.
### **Monitoring**
CTUIL, Independent Engineer, and CEA will monitor progress and report deviations to CERC.
—
For more information please see below link:


