DERC Extends Scheduled Delivery Date On account of Force Majeure

In the matter of: Petition seeking extension of Scheduled Delivery Date (SDD) under Section 86(1)(b), (e) and (f) of the Electricity Act, 2003 read with Article 4.1.1 read with Article 7 of the respective Power Purchase Agreements dated 15.07.2015 executed between M/s TPDDL and SEI Renewable Energy Private Ltd., SEI Jyotiswaroop Power Private Ltd. and […]

Petition by GIFT Power for Extension of Existing PPA With M/s PTC India

TNERC Rejects VSR Solar Power Petition for Extending Project Commissioning Deadline 

TNERC Rejects VSR Solar Power Petition for Extending Project Commissioning Deadline M/s VSR Solar Power Private Limited / Grant the Petitioner a project specific extension of the COD by eighteen months i.e. 21.3.2019 to 21.9.2020 in respect of the Petitioner’s SPG under PPA etc For more information please see below link:

Petition by GIFT Power for Extension of Existing PPA With M/s PTC India

Case of AMJ Land Holdings for removal of difficulties in implementation of Regulation 20.3 of the MERC (Distribution Open Access) (First Amendment)

  Case of AMJ Land Holdings Limited for removal of difficulties in implementation of Regulation 20.3 of the MERC (Distribution Open Access) (First Amendment) Regulations, 2019 related to banking issue due to Force Majeure situation prevailing in Maharashtra State on account of COVID-19 outbreak and lockdown For more information please see below link:

Petition by GIFT Power for Extension of Existing PPA With M/s PTC India

In the matter of: To specify a reduced rate (subject to maximum 6% per annum) of late payment surcharge(LPS) for payment which becomes delayed

In the matter of: Directions vide letter No. 01/04/2020-EB(PR)/180-182 dated 30.03.2020 Govt. of Punjab, Department of Power issued under Section 108 of the Electricity Act, 2003 to specify a reduced rate (subject to maximum 6% per annum) of late payment surcharge(LPS) for payment which becomes delayed beyond the due date during the period from 24.03.2020 […]

Petition by GIFT Power for Extension of Existing PPA With M/s PTC India

In the matter of: To specify a reduced rate of LPS for payment which becomes delayed beyond the due date

In the matter of: Directions vide letter No. 01/04/2020-EB(PR)/180-182 dated 30.03.2020 Govt. of Punjab, Department of Power issued under Section 108 of the Electricity Act, 2003 to specify a reduced rate (subject to maximum 6% per annum) of late payment surcharge(LPS) for payment which becomes delayed beyond the due date during the period from 24.03.2020 […]

Petition by GIFT Power for Extension of Existing PPA With M/s PTC India

Indian renewable energy agencies asked to treat lockdown as Force Majeure

This means renewable agencies should allow developers a suitable time frame to complete pending projects, on account of disrupted supply chains The Indian Government has granted a 30-day extension to all renewable energy agencies to normalise operations post the Covid-19 crisis. The Ministry of New and Renewable Energy has asked for the lockdown to be […]

Sterling & Wilson Solar Ltd Leads Losers in ‘A’ Group

Withdraw capacity charges on power utility, says Capt Amarinder Singh

Citing the nationwide lockdown in place since March 24, 2020, Captain Amarinder said,” Due to imposition of restrictions on the operations of all kinds of establishments, barring those providing essential services, the demand for power has resultantly been severely reduced.” CHANDIGARH: Punjab chief minister Captain Amarinder Singh on Monday urged the Union Power Ministry to […]

NSEFI Representation to UP govt on uncertainty prevailing the UP

Force Majeure should have built-in relief for incurred costs: Ashish Khanna, MD & CEO, Tata Power Solar and President, Tata Power Renewables

“The entire industry, not just Tata Power Solar is importing Chinese equipment and since we are an EPC contractor, we are importing even for clients” In the current situation of liquidity crunch, the renewable industry is in flux and we don’t foresee people investing in CAPEX right now tells Ashish Khanna, MD & CEO, Tata […]

EQ In Exclusive Conversation With Mr. Pankaj Dhingra, CEO & Mr. J.S. Bhatia, Head(Solar business) At BVG Clean Energy Ltd.

IREDA to handle CPSU Scheme on behalf of MNRE

The amended clause also added that all issues regarding time-extension and dispute resolution on force majeure events will also be dealt by IREDA New Delhi: The Ministry of New and Renewable Energy (MNRE) has appointed the Indian Renewable Energy Development Agency Limited (IREDA) as the implementing agency to handle the Central Public Sector Undertaking (CPSU) […]

NSEFI Representation to UP govt on uncertainty prevailing the UP