In the Matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations under System Strengthening Scheme in Northern Region–XXXVII (NRSS-XXXVII) – EQ

Summary: — **Key Dates & Delays** – **Asset-1:** SCOD – 19.12.2019, COD – 4.12.2022 → **Time overrun: 1081 days** – **Asset-2:** COD claimed as 5.1.2023 → Delay due to unready downstream asset by PTCUL. – **Asset-3:** COD claimed as 5.1.2023 → Delay due to washed-out bridge preventing reactor relocation. **PGCIL’s Claims** – **Asset-2:** COD claimed […]

Chhattisgarh State Electricity Supply Code (Fifth Amendment) 2025 – EQ