In the Matter of Approval the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations under System Strengthening Scheme in Northern Region–XXXVII (NRSS-XXXVII) – EQ

Summary: — **Key Dates & Delays** – **Asset-1:** SCOD – 19.12.2019, COD – 4.12.2022 → **Time overrun: 1081 days** – **Asset-2:** COD claimed as 5.1.2023 → Delay due to unready downstream asset by PTCUL. – **Asset-3:** COD claimed as 5.1.2023 → Delay due to washed-out bridge preventing reactor relocation. **PGCIL’s Claims** – **Asset-2:** COD claimed […]

Petition of the CERC (Connectivity and General Network Access to the interstate Transmission System) Regulations, 2022 – EQ

Petition for determination of transmission tariff from the COD to System Strengthening Scheme in the Northern Region–XXXVII (NRSS-XXXVII) – EQ

Summary: — **Case Details** – **Petition No:** 330/TT/2023 – **Subject:** Determination of transmission tariff from the Commercial Operation Date (COD) to 31.03.2024 for three assets under the *System Strengthening Scheme in the Northern Region–XXXXII (NRSS-XXXVII)* – **Petitioner:** Power Grid Corporation of India Limited (PGCIL) – **Respondents:** Power Transmission Corporation of Uttarakhand Limited (PTCUL) and 15 […]