Summary: — This order is a regulatory and financial roadmap for MSEDCL, balancing revenue recovery, tariff rationalization, and renewable energy integration, while aiming to modernize operations and ensure long-term sustainability. ### 1. Purpose of the Order – Issued by MSEDCL to formalize decisions on electricity distribution, tariffs, and operational compliance. – Aimed at ensuring financial […]
Petition for revision of tariff of Muzaffarpur Thermal Power Station Stage-I (220 MW) after the truing up exercise for the period from 1.4.2014 to 31.3.2019 KBUNL For more information please see below link:
Petition for revision of tariff for NLC Thermal Power Station (TPS-I) (600 MW) for the period 2014-19 after truing-up exercise. NLC India Limited. For more information please see below link:
Petition for revision of tariff for the 2014-19 tariff period after truing up exercise in respect of Bokaro Thermal Power Station Unit-1 to 3 (630 MW) and determination of tariff for the 2019-24 tariff period. For more information please see below link:
Petition for revision of tariff for the 2014-19 tariff period in respect of Koteshwar Hydro Power Station (400 MW). THDC India Limited. For more information please see below link: