Petition for truing up and determination of the transmission tariff fior “Provision of Spare Transformers and Reactors” in the North Eastern Region of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations – EQ

Summary: —- **Key Approved Components:** **1. Trued-up Tariff (2019-24):** – **Capital Cost:** Approved as on 1.4.2019: ₹1125.03 lakh; as on 31.3.2024: ₹1138.41 lakh. – **Additional Capital Expenditure (ACE):** ₹13.38 lakh allowed (balance/retention payments). – **Debt-Equity Ratio:** Maintained at 70:30. – **Annual Fixed Charges (AFC):** Approved as under (₹ in lakh): | Year | 2019-20 | […]

Petition of the CERC (Procedure, Terms and Conditions for grant of Trading Licence and other related matters) Regulations for upgradation of inter-state trading licence in electricity – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for Truing up and determination of the transmission tariff with System Strengthening for Western and Northern Region – EQ

Summary: —- #### 1. Purpose of the Petition This petition was filed by POWERGRID for two primary purposes regarding a set of transmission assets (“the Combined Assets”): 1. **True-up of Tariff (2019-24):** To reconcile the provisional transmission tariffs approved for the 2019-24 period with the actual audited costs incurred by the company. 2. **Determination of […]

Petition of the CERC (Procedure, Terms and Conditions for grant of Trading Licence and other related matters) Regulations for upgradation of inter-state trading licence in electricity – EQ

Petition for Truing up and determination of the transmission tariff for Combined Asset under “Northern Region System Strengthening Scheme-XV” – EQ

Summary: — ### **1. PROCEEDINGS & COMMISSION’S DIRECTIONS** After hearing PGCIL’s representatives, the Commission issued the following procedural directions: **A. Timeline for Submissions:** 1. **Respondents** (State Utilities) to file their **replies within two weeks**, with an advance copy to PGCIL. 2. **PGCIL** may file its **rejoinder within two weeks** thereafter. **B. Specific Information Sought from […]

Petition of the CERC (Procedure, Terms and Conditions for grant of Trading Licence and other related matters) Regulations for upgradation of inter-state trading licence in electricity – EQ

Petition of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for the Combined Assets under “POWERGRID works associated with System Strengthening for IPPs in Chhattisgarh and other generation projects in Western Region” – EQ

Summary: — **1. Overview & Context** * **Document Type:** CERC Order/Proceeding from a hearing held on **13 January 2026**. * **Core Subject:** Admission and initial hearing of three (3) separate tariff petitions filed by the **Power Grid Corporation of India Limited (PGCIL)**. * **Regulatory Framework:** Petitions filed under the **Electricity Act, 2003** and the **CERC’s […]

Petition of the CERC (Procedure, Terms and Conditions for grant of Trading Licence and other related matters) Regulations for upgradation of inter-state trading licence in electricity – EQ

Petition for Truing up and determination of the transmission tariff for “Northern Region System Strengthening Scheme XXXIV” in the Northern Region – EQ

Summary: — ## **Case Overview** This document consolidates proceedings for **nine petitions** filed by **Power Grid Corporation of India Ltd. (PGCIL)** relating to **truing up of transmission tariff (2019–24)** and determination of tariff for the **2024–29 period**. ### **Petition-wise Breakdown** 1. **Petition 481/TT/2025** – Northern Region System Strengthening Scheme XXXIV. 2. **Petition 512/TT/2025** – Northern […]

Petition of the CERC (Procedure, Terms and Conditions for grant of Trading Licence and other related matters) Regulations for upgradation of inter-state trading licence in electricity – EQ