1. Home
  2. Tag "Taluka-Valia"

Petition of GERC (Conduct of Business) Regulations and Gujarat Renewable Energy Policy for commissioning of 4 MW AC Solar Power Project at Village – Dungri, Taluka-Valia District Bharuch – EQ

Summary: —- #### 1. Core Dispute: Delay in Project Commissioning – **The Project:** A 4.00 MW (3.90 MW AC) solar power project under the **captive use category**. – **Petitioner’s Argument for Delay:** The developer blamed the utilities for delays in signing the connection agreement and providing estimates for supervision charges. They claimed the agreement was […]

Petition of the CERC (Sharing of Inter-State Transmission Charges and Losses) Regulations for RSPPL and Ors. – EQ