Petition with CERC (Procedure, Terms and Conditions for Grant of Transmission License and other related matters) Regulations to POWERGRID Barmer I Transmission Limited – EQ
Summary:
—
## ⚖️ **Case Summary – CERC Petition No. 789/TL/2025**
* **Authority:** Central Electricity Regulatory Commission (CERC), New Delhi
* **Date of Hearing:** 26 September 2025
* **Coram:**
* Shri Jishnu Barua – Chairperson
* Shri Ramesh Babu V. – Member
* Shri Harish Dudani – Member
* Shri Ravinder Singh Dhillon – Member
—
## ⚙️ **Petition Overview**
* **Filed under:** Section 14 of the *Electricity Act, 2003*, read with
*CERC (Procedure, Terms and Conditions for Grant of Transmission License and Other Related Matters) Regulations, 2024*.
* **Purpose:** Request for **grant of a separate RTM (Regulated Tariff Mechanism) Transmission Licence**.
* **Transmission Project:**
“Implementation of **one 220 kV line bay** for interconnection of **M/s Anboto Solar Pvt. Ltd.** (300 MW total: 250 MW + 50 MW) **Renewable Energy Power Projects** at **765/400/220 kV Barmer-I Pooling Station (PS)**.”
* **Mode:** Regulated Tariff Mechanism (RTM).
—
## 🏢 **Parties**
* **Petitioner:** *POWERGRID Barmer I Transmission Limited (BITL)*
* **Respondents:** *Central Transmission Utility of India Limited (CTUIL) and Others*
* **Representatives:**
* Ms. Tanushree Rao (BITL)
* Shri Akshayvat Kislay, Shri Ranjeet S. Rajput, Shri Swapnil Verma (CTUIL)
—
## 🧾 **Proceedings and Directions**
1. **Petition admitted**; notice issued to all respondents.
2. **Replies** to be filed within **2 weeks**; petitioner may file **rejoinder within 1 week** thereafter.
3. **Next hearing scheduled for:** **22 October 2025**.
—
## 📄 **Current Status (as of 26 Sep 2025)**
* Petition **admitted**; CERC has taken up BITL’s request for a **dedicated transmission licence** under RTM mode.
* Awaiting responses from CTUIL and other respondents before the next hearing.
—
For more information please see below link: