1. Home
  2. Policy & Regulation
  3. In the matter of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff for Hiriyur and Kochi Sub-stations” in the Southern Region – EQ
In the matter of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff for Hiriyur and Kochi Sub-stations” in the Southern Region – EQ

In the matter of the CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for truing up and determination of the transmission tariff for Hiriyur and Kochi Sub-stations” in the Southern Region – EQ

0
0

Summary:

## 1. Case Overview

| Parameter | Details |
|———–|———|
| **Petition Number** | 559/TT/2025 |
| **Order Date** | January 20, 2026 |
| **Petitioner** | Power Grid Corporation of India Limited (PGCIL) |
| **Respondents** | 14 Distribution Companies across Southern Region |
| **Regulatory Framework** | CERC Tariff Regulations, 2019 (for truing up) and 2024 (for new tariff period) |
| **Purpose** | Truing up of tariff for 2019-24 and determination of tariff for 2024-29 for augmentation project at Hiriyur and Kochi substations |

## 2. Project Details

### 2.1 Asset Description

| Asset No. | Asset Name | Location | COD |
|———–|————|———-|—–|
| **Asset-1** | 1 x 500 MVA, 400/220 kV Transformer along with associated bays | Hiriyur Substation | October 31, 2022 |
| **Asset-2** | 1 x 500 MVA, 400/220 kV Transformer along with associated bays | Kochi Substation | July 15, 2023 |
| **Combined Asset** | Both assets combined for tariff determination | – | Effective COD: February 27, 2023 |

### 2.2 Project Scope

| Component | Hiriyur Substation | Kochi Substation |
|———–|——————-|——————|
| **400 kV ICT Bay** | 1 No. | 1 No. |
| **500 MVA, 400/220 kV ICT** | 1 No. | 1 No. |
| **220 kV ICT Bay** | 1 No. | 1 No. |

### 2.3 Project Timeline

| Milestone | Date |
|———–|——|
| **Project Discussion (1st SRSCT Meeting)** | September 7, 2018 |
| **Final Agreement (2nd SRPC TP Meeting)** | October 1, 2020 |
| **Investment Approval (IA)** | October 26, 2021 |
| **IA Communication Date** | October 27, 2021 |
| **Asset-1 COD** | October 31, 2022 |
| **Asset-2 COD** | July 15, 2023 |
| **Effective COD (Combined Asset)** | February 27, 2023 |

### 2.4 Cost Details

| Parameter | Amount (₹ Lakh) |
|———–|——————|
| **Original FR Cost (June 2021 price level)** | 9,351.00 |
| **IDC included in FR** | 258.00 |
| **Asset-1 Capital Cost as on COD (allowed)** | 2,843.51 |
| **Asset-2 Capital Cost as on COD (allowed)** | 3,144.39 |
| **Total Capital Cost as on COD** | 5,987.90 |
| **ACE (2019-24) – Asset-1** | 958.55 |
| **ACE (2019-24) – Asset-2** | 154.66 |
| **Total Capital Cost as on 31.3.2024** | **7,101.11** |
| **Projected ACE (2024-29)** | 2,134.65 |
| **Total Capital Cost as on 31.3.2029** | **9,235.76** |

## 3. Key Issues and Decisions

### 3.1 Time Overrun Analysis

| Asset | SCOD | COD | Time Overrun | Condoned | Not Condoned |
|——-|——|—–|————–|———-|————–|
| **Asset-1** | October 31, 2022 | October 31, 2022 | **Nil** | – | – |
| **Asset-2** | Not specified | July 15, 2023 | **257 days** | 69 days | 188 days |

**Reason for Delay (Asset-2):** The detailed reasons for the 257-day delay in commissioning the Kochi substation transformer were examined, with 69 days condoned and 188 days attributed to controllable factors, resulting in disallowance of IDC/IEDC for the uncondoned period.

### 3.2 Effective Date of Commercial Operation (E-COD)

**Petitioner’s Submission:**
– Combined Asset E-COD calculated as February 27, 2023
– Based on weighted average of individual asset CODs and capital costs

**KSEBL’s Objection:**
– Discrepancy noted between E-COD mentioned in petition and tariff forms

**Petitioner’s Response:**
– Typographical error acknowledged
– Confirmed E-COD as February 27, 2023

**Commission’s Decision:**
✅ **E-COD approved as February 27, 2023**
✅ Lapsed life as on April 1, 2024: **1 year**
✅ Remaining useful life: **24 years**

## 4. Truing Up of Tariff (2019-24 Period)

### 4.1 Capital Cost Trued Up

| Asset | Capital Cost as on COD (₹ Lakh) | ACE Allowed (₹ Lakh) | Capital Cost as on 31.3.2024 (₹ Lakh) |
|——-|——————————–|———————-|————————————–|
| **Asset-1** | 2,843.51 | 958.55 | 3,802.06 |
| **Asset-2** | 3,144.39 | 154.66 | 3,299.05 |
| **Total** | **5,987.90** | **1,113.21** | **7,101.11** |

### 4.2 ACE Details (2019-24)

**Asset-1 ACE Breakdown:**

| Party Name | Particulars | Outstanding Liability as on COD | Discharge of Liability (₹ Lakh) |
|————|————-|——————————–|——————————–|
| M/s Linxon India Pvt Ltd | Sub-station | 1,336.39 | 457.15 |
| M/s Toshiba T&D System | Sub-station | 649.75 | 160.92 |
| Community Hall | Building and Civil Works | 50.00 | 50.00 |
| IDC Discharge | – | – | 12.57 |
| Misc Site Packages | – | – | 237.42 |
| **Total** | | | **958.55** |

**Asset-2 ACE Breakdown:**

| Party Name | Particulars | Outstanding Liability as on COD | Discharge of Liability (₹ Lakh) |
|————|————-|——————————–|——————————–|
| Construction of Boundary Wall | Building and Civil Works | 111.00 | 0.00 |
| Construction of additional rooms | Building and Civil Works | 56.02 | 0.00 |
| Site Levelling | Building and Civil Works | 70.00 | 0.00 |
| Other items | – | – | 154.66 |
| **Total** | | | **154.66** |

### 4.3 Annual Fixed Charges – Trued Up (2019-24)

**Asset-1:**
| Particulars | 2022-23 (Pro-rata 152 days) | 2023-24 |
|————-|——————————|———|
| Depreciation | 71.72 | 197.53 |
| Interest on Loan | 74.12 | 199.33 |
| Return on Equity | 76.54 | 210.80 |
| O&M Expenses | 108.12 | 268.25 |
| Interest on Working Capital | 7.02 | 20.74 |
| **Total AFC** | **337.51** | **896.65** |

**Asset-2:**
| Particulars | 2023-24 (Pro-rata 261 days) |
|————-|——————————|
| Depreciation | 123.43 |
| Interest on Loan | 117.31 |
| Return on Equity | 129.45 |
| O&M Expenses | 191.29 |
| Interest on Working Capital | 13.84 |
| **Total AFC** | **575.33** |

### 4.4 Comparison: Previous Order vs. Trued Up

**Asset-1:**
| Year | Previous Order (₹ Lakh) | Trued Up (₹ Lakh) | Difference |
|——|————————|——————-|————|
| 2022-23* | 345.07 | 337.51 | -7.56 |
| 2023-24 | 993.74 | 896.65 | -97.09 |

**Asset-2:**
| Year | Previous Order (₹ Lakh) | Trued Up (₹ Lakh) | Difference |
|——|————————|——————-|————|
| 2023-24* | 597.16 | 575.33 | -21.83 |

*Pro-rata periods

## 5. Tariff Determination (2024-29 Period)

### 5.1 Combined Asset Capital Cost

| Year | Opening Capital Cost (₹ Lakh) | ACE Added (₹ Lakh) | Closing Capital Cost (₹ Lakh) |
|——|——————————-|——————–|——————————-|
| **1.4.2024** | 7,101.11 | – | – |
| **2024-25** | 7,101.11 | 1,652.74 | 8,753.85 |
| **2025-26** | 8,753.85 | 481.91 | 9,235.76 |
| **2026-27** | 9,235.76 | 0.00 | 9,235.76 |
| **2027-28** | 9,235.76 | 0.00 | 9,235.76 |
| **2028-29** | 9,235.76 | 0.00 | 9,235.76 |
| **As on 31.3.2029** | – | **2,134.65** | **9,235.76** |

### 5.2 ACE Details (2024-29 Projected)

**Asset-1 ACE Projection:**

| Party Name | Particulars | Outstanding as on 31.3.2024 | Discharge (₹ Lakh) |
|————|————-|—————————–|——————-|
| M/s Linxon India Pvt Ltd | Sub-station | 879.24 | 879.24 |
| M/s Toshiba T&D System | Sub-station | 160.92 | 160.92 |
| Community Hall | Building and Civil Works | 50.00 | 50.00 |
| **Total Asset-1** | | **1,090.16** | **1,090.16** |

**Asset-2 ACE Projection:**

| Party Name | Particulars | Outstanding as on 31.3.2024 | Discharge (₹ Lakh) |
|————|————-|—————————–|——————-|
| Construction of Boundary Wall | Building and Civil Works | 111.00 | 111.00 |
| **Total Asset-2** | | **111.00** | **111.00** |

**Year-wise ACE:**
| Year | Asset-1 (₹ Lakh) | Asset-2 (₹ Lakh) | Total (₹ Lakh) |
|——|——————|——————|—————-|
| **2024-25** | 1,586.14 | 66.60 | 1,652.74 |
| **2025-26** | 252.92 | 44.40 | 297.32* |
| **Total** | **1,839.06** | **111.00** | **1,950.06*** |

*Note: The order shows total ACE of ₹2,134.65 lakh for 2024-29, which includes additional amounts beyond the detailed vendor-wise breakdown

### 5.3 Debt-Equity Structure (Combined Asset)

| Funding | As on 1.4.2024 | ACE (2024-29) | As on 31.3.2029 |
|———|—————-|—————|—————–|
| **Debt** | ₹4,970.78 lakh (70%) | ₹1,494.26 lakh (70%) | ₹6,465.03 lakh (70%) |
| **Equity** | ₹2,130.33 lakh (30%) | ₹640.40 lakh (30%) | ₹2,770.73 lakh (30%) |
| **Total** | **₹7,101.11 lakh** | **₹2,134.65 lakh** | **₹9,235.76 lakh** |

### 5.4 Weighted Average Life (WAL) Calculation

| Element | Capital Cost as on 31.3.2024 (₹ Lakh) | Life (Years) | Weighted Life |
|———|—————————————|————–|—————|
| **Land** | 0.00 | – | – |
| **Building** | 0.00 | – | – |
| **Sub-station** | 6,803.17 | 25 | 170,079.25 |
| **PLCC** | 297.94 | 15 | 4,469.10 |
| **Total** | **7,101.11** | | **174,548.35** |

**WAL = 174,548.35 / 7,101.11 = 24.58 years ≈ 25 years**

### 5.5 Annual Fixed Charges (2024-29) – Combined Asset

| Particulars | 2024-25 | 2025-26 | 2026-27 | 2027-28 | 2028-29 |
|————-|———|———|———|———|———|
| Depreciation | 418.79 | 470.84 | 482.02 | 482.02 | 482.02 |
| Interest on Loan | 387.67 | 411.67 | 387.61 | 349.88 | 312.17 |
| Return on Equity | 446.68 | 506.82 | 520.40 | 520.40 | 520.40 |
| Interest on Working Capital | 34.27 | 37.12 | 37.98 | 38.24 | 38.75 |
| O&M Expenses | 362.40 | 381.66 | 401.22 | 422.06 | 445.18 |
| **Total AFC** | **1,649.81** | **1,808.12** | **1,829.23** | **1,812.60** | **1,798.51** |

### 5.6 Comparison: Claimed vs. Allowed (2024-29)

| Year | Claimed (₹ Lakh) | Allowed (₹ Lakh) | Difference |
|——|——————|——————|————|
| **2024-25** | 1,649.81 | 1,649.81 | 0.00 |
| **2025-26** | 1,808.12 | 1,808.12 | 0.00 |
| **2026-27** | 1,829.23 | 1,829.23 | 0.00 |
| **2027-28** | 1,812.61 | 1,812.60 | -0.01 |
| **2028-29** | 1,798.52 | 1,798.51 | -0.01 |

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network