1. Home
  2. Policy & Regulation
  3. Petition for the Adoption of tariff for 420 MW RTC power from ISTS-connected RE Power Projects (SECIRTC- IV) by the Ministry of Power, Government of India – EQ
Petition for the Adoption of tariff for 420 MW RTC power from ISTS-connected RE Power Projects (SECIRTC- IV) by the Ministry of Power, Government of India – EQ

Petition for the Adoption of tariff for 420 MW RTC power from ISTS-connected RE Power Projects (SECIRTC- IV) by the Ministry of Power, Government of India – EQ

0
0

Summary:

## **1. Purpose of the Petition**

SECI filed the petition under **Section 63 of the Electricity Act, 2003** seeking CERC’s approval for:

1. Adoption of tariff discovered through competitive bidding for **420 MW RTC renewable power** under SECI-RTC-IV.
2. Approval of **₹0.07/kWh trading margin**.

This procurement is under the **MoP Guidelines dated 9 June 2023** for “firm and dispatchable renewable power with energy storage”.

## **2. Background and Bidding Framework**

SECI, acting as the **Renewable Energy Implementing Agency (REIA)**, issued the **RfS on 28 October 2024** for **1200 MW RTC renewable energy** with ESS.
The bidding process included:

* Multiple corrigenda/amendments from Oct 2024 to Mar 2025
* Pre-bid meeting on 14 November 2024
* Submission deadline: 24 March 2025
* Financial bid opening: 26 May 2025
* E-reverse auction: 26 May 2025

A total of **5 bidders** submitted techno-commercially qualified bids for **540 MW**.

## **3. Competitive Bidding Outcome**

After the e-Reverse Auction on **26 May 2025**, SECI awarded **420 MW** as follows:

| Bidder | Capacity (MW) | Tariff (₹/kWh) |
| ——————————– | ————- | ————– |
| Hero Solar Energy Pvt. Ltd. | 120 | 5.06 |
| Hexa Climate Solutions Pvt. Ltd. | 100 | 5.06 |
| Sembcorp Green Infra Pvt. Ltd. | 50 | 5.07 |
| Jindal India Power Ltd. | 150 | 5.07 |

LoAs were issued on **11 June 2025**.

## **4. SECI’s Submissions on Tariff Reasonableness**

SECI provided certificates from the **Bid Evaluation Committee (BEC)** confirming that:

### **i. Tender is first-of-its-kind RTC structure**

* Requires high firmness and dispatchability
* Demands **100% annual RE power**
* Includes stringent performance metrics using **Demand Fulfilment Ratio (DFR)**

* **Monthly DFR ≥ 75%**
* **Annual DFR ≥ 80%**
* **Peak-hour DFR ≥ 90%**
* Penalties apply for shortfall

### **ii. The tariff reflects higher RTC obligations**

Compared with SJVN’s FDRE-3 tender (Feb 2025) with tariffs **₹4.82–4.91/kWh**, the RTC-IV tender is more stringent, requiring:

* Higher storage
* Better dispatch optimisation
* Higher reliability
* More complex resource integration

Thus, the discovered tariff **₹5.06–5.07/kWh** is considered fair.

### **iii. Market changes influenced the price**

Supply chain, cost of storage, financing conditions, and increased reliability needs contributed to the final tariff.

## **5. CERC’s Analysis**

CERC examined:

* The entire RfS and bidding chronology
* Compliance with MoP Guidelines
* SECI’s conformity certificates
* BEC’s justification on tariff reasonableness

CERC found:

### **A. Process was transparent and guideline-compliant**

The bidding steps strictly followed the MoP 2023 Guidelines.

### **B. Minimum competition requirements met**

Five technically qualified bidders ensured competitive price discovery.

### **C. Evaluation Committee duly certified compliance**

All conformity certificates and tariff reasonableness assessments were in order.

### **D. No objections from respondents**

None of the four respondents filed replies against the bidding process or discovered tariff.

For more information please see below link:

Anand Gupta Editor - EQ Int'l Media Network