Petition of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for the Transmission System – EQ

Petition of CERC (Conduct of Business) and (Terms and Conditions of Tariff) Regulations for the Transmission System – EQ

0
0

Summary:

## **Case Details**

* **Petitioner**: *Patran Transmission Company Private Limited (PTCL)*
* **Respondents**: *Central Transmission Utility of India Limited (CTUIL) and others*
* **Subject**: Petition for **determination of transmission tariff** from **COD to 31.03.2029** under the CERC Tariff Regulations, 2024.
* **Asset Involved**:

* *Augmentation of Transformation Capacity* by **1×500 MVA, 400/200 kV ICT (3rd)** at **Patran GIS Substation**.
* Includes GIS ducting at **400 kV and 220 kV** in a new diameter of ICT tie-line.
* **Hearing Date**: 26.08.2025
* **Coram**: Chairperson Shri Jishnu Barua and Members Shri Ramesh Babu V., Shri Harish Dudani, Shri Ravinder Singh Dhillon.

## **Commission’s Directions**

1. **Notice & Replies**

* Notices to be issued to all respondents.
* Respondents to file replies within **two weeks**; Petitioner may file rejoinder within **one week** thereafter.

2. **Additional Information Required from Petitioner (to be filed on affidavit within two weeks)**

* **Cost Discrepancy**:

* CTUIL estimated cost: ₹65.19 crore.
* Awarded cost: ₹79.85 crore.
* Completion cost difference: \~₹9.41 crore.
* Petitioner to explain reasons for higher awarded cost.
* **Revised Cost Estimate (RCE)**:

* CTUIL Resolution (28.02.2025): ₹8926.00 lakh.
* Petition filed figure: ₹9651.00 lakh.
* Clarification required on discrepancy.
* **Revised Forms**:

* Form-5 (with FR cost, RCE, estimated completion cost).
* Form-12.
* Form-13 (initial spares).
* **Liability Flow Statement**.
* **Initial Spares Discrepancy**:

* Auditor’s certificate: ₹212.99 lakh.
* Form-13: ₹399.60 lakh.
* Clarification and revised auditor’s certificate required.
* **Security Costs**:

* Provide assessment of security needs for 2024–29 period.
* State whether security already deployed at Patran GIS substation.
* Justify any *additional* security charges claimed for ICT under the petition.

## **Next Steps**

* The Petition is scheduled for **next hearing on 21.10.2025**.
* Compliance with the above directions will form the basis for further consideration of tariff determination.